staff report memo · L-3

Tiffin Recreation Center Monthly Report — L.3

Open the PDF

Page 11 of 18

Text from the PDF text layer; check the PDF for anything that matters.
Progress Photos Shower room walls being laid out Shower room stud installation Concession stand window framed out Sink installation in shower rooms Additional blocking and rough-in in 2nd Floor walls being laid out shower rooms Owner Progress Report | 250120 April 2026 Miron Construction Co., Inc. | 11