Construction Summary Schedule Update Scheduled July Activities: Scheduled August Activities: • Hang and finish drywall (95%) • Finish painting • Exterior signage install (65%) • 2nd floor athletic flooring install • Exterior aluminum frames and glass (98%) • Exterior grading beginning • Elevator installation (98%) • Exterior signage install • Painting (40%) Manpower Report List of major subcontractors & number of employees onsite (monthly average): Total number of employees: 49 • AAA Mechanical – 3 • Miron Construction Manager – 2 • Appleby and Horn – 2 • Otis Elevator Systems – 2 • Culver’s Landscape – 3 • Pearson Wall Systems – 3 • Hargers Acoustics – 2 • Price Electric – 7 • H2I Group – 8 • Seehase Masonry – 2 • Ilten’s – 2 • Tri-City Fire Protection – 1 • Merit Construction – 4 • Youngs Painting & Decorating - 3 • Miron Concrete/General Trades – 3 • Zephyr Aluminum - 2 Delays • Weather – See Daily Log Weather Report • N/A • Weather delays are no longer on critical path and will be removed. • Materials & Labor ‒ N/A Key Issues / Concerns & Recommended Action Steps • Painting ‒ Adding additional crews Deliver unmatched quality, create meaningful connections, and craft unforgettable experiences in everything we do. Capture what truly matters and find ways to inspire. Owner Progress Report | 250120 July 2026 Miron Construction Co., Inc. | 8

Sources

Attached to agenda item: L-1 Tiffin Recreation Center Monthly Report – July 2026

This document's details as JSON

Data last updated October 15, 2026. Built from the archive's documents; see how the data is built.