Tiffin Recreation Center Monthly Report – July 2026 — L-1
Page 17 of 17
Text from the PDF text layer; check the PDF for anything that matters. Tiffin Community Recreation Center Layout Name: 250120B
Construction Schedule Update 08/07/2026
Miron Construction Co., Inc. Data Date: 07-Aug-26
Page 3 of 3
250120-60PM 20260807
Activity ID Resp PredecessorsSuccessors Activity Name Orig Rem Start Finish 2026
Dur Dur
Aug Sep Oct Nov
1760 MIRON 1740, 1770 Quality Control Review 5 5 13-Oct-26 19-Oct-26
1950,
1770 MIRON 1880,
1760 1780, Punchlist 6 6 20-Oct-26 27-Oct-26
1890
1780 MIRON 3540, 1790 Substantial Completion 0 0 27-Oct-26*
1770,
1790 MIRON 1890
1780 1800 Punchlist Corrections 5 5 28-Oct-26 03-Nov-26
1800 MIRON 1790 Final Completion 0 0 03-Nov-26
Actual Work
Remaining Work Please review the activities for which you are responsible and the relationships to the activities of other
Critical Remaining Work trades. If you have questions or comments, please contact Patrick Myers & Corey Boyles immediately. If
Milestone we receive no comments from you by 5 workings days, we will assume a lack of response to be your
agreement and commitment to the durations, relationships, and sequencing of this plan. As always, we will
attempt to improve upon the dates shown. Periodic updates will be distributed as the project progresses.
Sources
- revize: L-1 (HMHfrhcQEul79QQuV1K6O7Vu3vkqUQ.pdf) — where it was found ↗ first seen Oct 12, 2026
Attached to agenda item: L-1 Tiffin Recreation Center Monthly Report – July 2026
Data last updated October 16, 2026. Built from the archive's documents; see how the data is built.