Construction Schedule Update 08/07/2026
Miron Construction Co., Inc. Data Date: 07-Aug-26
Page 1 of 3
250120-60PM 20260807
Activity ID Resp PredecessorsSuccessors Activity Name Orig Rem Start Finish 2026
Dur Dur
Aug Sep Oct Nov
Tiffin Community Recreation Center 96 61 19-Jun-26 A 03-Nov-26
PRECONSTRUCTION 0 0
PRECONSTRUCTION - BP1 0 0
PRECONSTRUCTION - BP2 0 0
SUBMITTALS 0 0
A/E REVIEW / APPROVAL 0 0
FAB / DELIVER 50 40 27-Jul-26 A 05-Oct-26
3480 TSF 3450 Metal Louver - Fab and Delivery 50 40 27-Jul-26 A 05-Oct-26
SITEWORK 70 45 08-Jul-26 A 12-Oct-26
3470 MEDIA 1840 2120 Exterior Signage Install 5 2 08-Jul-26 A 11-Aug-26
2120 SCHRADER 3440, 1940 Rough Grade 5 3 06-Aug-26 A 14-Aug-26
3460,
1940 ALL AMERICAN 3470
2120 1950, Site Concrete - Curbs and Sidewalks 8 8 17-Aug-26 26-Aug-26
1960
1960 SCHRADER 2430, 1870 Final Grade 5 5 27-Aug-26 02-Sep-26
1340,
1950 LLPELL 1940
1940 1760 Asphalt Grind and Striping 5 5 27-Aug-26 02-Sep-26
1870 CULVERS 1440, 1760 Landscape 10 10 03-Sep-26 17-Sep-26
1960
3450 TSF 3480 1760 Metal Louvers 5 5 06-Oct-26 12-Oct-26
CONSTRUCTION 85 50 19-Jun-26 A 19-Oct-26
1st Floor 85 50 19-Jun-26 A 19-Oct-26
3390 PEARSON 3360, 3010, 1st Floor North Drywall - Tape and Finish 10 3 19-Jun-26 A 12-Aug-26
3360 3330,
1630 HARGERS 3330, 2090
2880, 1st Floor Ceiling Tile - Grid 15 13 14-Jul-26 A 23-Sep-26
3490, 3550,
1640 AAAMECH 3510
3020, 1650,
1760 1st Floor Plumbing Fixtures 5 3 22-Jul-26 A 04-Sep-26
2080
3330 YOUNGS 3390 3490, 1st Floor Paint - North 10 4 30-Jul-26 A 18-Aug-26
2920,
3510 YOUNGS 3340 1630
3490, 1st Floor Paint - Hallway/Lobby/Concession/Community Room 11 6 31-Jul-26 A 27-Aug-26
2920, Walls
3340 YOUNGS 2940 2870,
3490, 1st Floor Ceiling Paint 10 8 06-Aug-26 A 19-Aug-26
3500,
3350 YOUNGS 1680 3510
1720 Paint - Stairs and Handrail 10 10 10-Aug-26 21-Aug-26
2090 ILTENS 3380, 1820 Full HVAC Startup 3 3 13-Aug-26 17-Aug-26
3390
3500 PRICEELEC 3340 3550, 1st Floor - Electrical Lights 10 10 20-Aug-26 02-Sep-26
1650,
1720 H2I 1970, 1730
1820, Wood Flooring - Gym Area 30 30 24-Aug-26* 05-Oct-26
3350, 2860
2860 PHILLIPSFLR 2890,
1720, 1760 Athletic Flooring - 1st Floor (AF-1) 15 15 24-Aug-26* 14-Sep-26
3400
1730 PHILLIPSFLR 3240, 1760, Flooring - Turf Area 3 3 25-Aug-26 27-Aug-26
2910, 3420
2080 GENTRADES 3500
3100, 1760, Architectural Casework Install 15 15 28-Aug-26 18-Sep-26
3510 1640
2870 PRICEELEC 3270, 3520, 1st Floor - Electrical Trim 10 10 28-Aug-26 11-Sep-26
3410, 1650
3510
Actual Work
Remaining Work Please review the activities for which you are responsible and the relationships to the activities of other
Critical Remaining Work trades. If you have questions or comments, please contact Patrick Myers & Corey Boyles immediately. If
Milestone we receive no comments from you by 5 workings days, we will assume a lack of response to be your
agreement and commitment to the durations, relationships, and sequencing of this plan. As always, we will
attempt to improve upon the dates shown. Periodic updates will be distributed as the project progresses.
Sources
- revize: L-1 (HMHfrhcQEul79QQuV1K6O7Vu3vkqUQ.pdf) — where it was found ↗ first seen Oct 12, 2026
Attached to agenda item: L-1 Tiffin Recreation Center Monthly Report – July 2026
Data last updated October 16, 2026. Built from the archive's documents; see how the data is built.