staff report memo · L-1

Tiffin Recreation Center Monthly Report – July 2026 — L-1

Open the PDF

Page 16 of 17

Text from the PDF text layer; check the PDF for anything that matters.
Tiffin Community Recreation Center Layout Name: 250120B Construction Schedule Update 08/07/2026 Miron Construction Co., Inc. Data Date: 07-Aug-26 Page 2 of 3 250120-60PM 20260807 Activity ID Resp PredecessorsSuccessors Activity Name Orig Rem Start Finish 2026 Dur Dur Aug Sep Oct Nov 2920 MIRON DOOR 3330, 1820 Interior Door and Harware Installation 5 5 28-Aug-26 03-Sep-26 3510, 3420 H2I 3320, 1730 1760 Wall/Column Padding Installation 3 3 28-Aug-26* 01-Sep-26 3490 PRICEELEC 3510, 3530, Low Voltage/Communications 15 15 28-Aug-26 18-Sep-26 3330, 1630 3250 TRI CITY FP 3340 1630 1760 Fire Protection - Trim Out Heads 4 4 04-Sep-26 10-Sep-26 2880 ILTENS 1630, 1820 1st Floor - Diffusers 5 5 21-Sep-26 25-Sep-26 1630 1740 APPLEBY 1630 1760 Soft Goods Flooring - 1st Floor 10 10 24-Sep-26 07-Oct-26 3550 MIRON 2890, 1650 Overhead Ceiling Inpections Complete 1 1 24-Sep-26 24-Sep-26 3500, 1650 CEILING 1630 3550, 1820 1st Floor Ceiling Tile - Drop 2 2 25-Sep-26 28-Sep-26 2870, 3520 PRICEELEC 1630, 2890, 3540, Fire Alarm Testing Complete 1 1 02-Oct-26 02-Oct-26* 2870 3530 1820 MEP 2920, 1880 Test & Balance 5 5 06-Oct-26 12-Oct-26 2880, 3530 OTIS 2900, 3490, 3540 Elevator Inspection 1 1 07-Oct-26 07-Oct-26* 3520 3540 MIRON 3520, 1780 Fire Marshall Inspection 1 1 08-Oct-26 08-Oct-26* 3530 1880 MEP 1820 1760 Commissioning 5 5 13-Oct-26 19-Oct-26 2nd Floor 54 30 07-Jul-26 A 21-Sep-26 3320 YOUNGS 1680, 2920, Paint - 2nd Floor Restroom Core 3 1 07-Jul-26 A 10-Aug-26 1670 3010 2890 PRICEELEC 1990, 3520, 2nd Floor - Electrical Trim and Lights 10 2 20-Jul-26 A 11-Aug-26 1680 3400, 3080 YOUNGS 1680 3550, 3410 Paint - 2nd Floor Mezzanine 10 3 29-Jul-26 A 12-Aug-26 3010 APPLEBY 3390, 1700 2nd Floor RR Skim Coat and Paint Change 8 2 05-Aug-26 A 14-Aug-26 3320 2900 ILTENS 1680 3400, 2nd Floor - Fabric Duct and Diffusers 8 8 10-Aug-26 19-Aug-26 1820, 1700 AAAMECH 3010 1720, 1760 2nd Floor Plumbing Fixtures 5 5 20-Aug-26 26-Aug-26 3400 PHILLIPSFLR 2890, 1810, Athletic Flooring - 2nd Floor (AF-2 Weights) 5 5 24-Aug-26* 28-Aug-26 2900 2860 1810 PHILLIPSFLR 3400, 1760 Athletic Flooring - 2nd Floor (AF-3 Track) 15 15 31-Aug-26 21-Sep-26 2890, WEATHER CONTINGENCY 2900 0 0 10-Aug-26 10-Aug-26 WEATHER CONTINGENCY SITE WORK BP1 0 0 10-Aug-26 10-Aug-26 1750 MIRON 2040 Weather Contingency Sitework (May '25-July'25 6 Days) 0 0 10-Aug-26 10-Aug-26 CRITICAL 0 0 NON-CRITICAL 0 0 WEATHER CONTINGENCY CONSTRUCTION BP2 0 0 CRITICAL 0 0 NON-CRITICAL 0 0 CONSTRUCTION BULLETINS 0 0 PROJECT COMPLETION 16 16 13-Oct-26 03-Nov-26 Actual Work Remaining Work Please review the activities for which you are responsible and the relationships to the activities of other Critical Remaining Work trades. If you have questions or comments, please contact Patrick Myers & Corey Boyles immediately. If Milestone we receive no comments from you by 5 workings days, we will assume a lack of response to be your agreement and commitment to the durations, relationships, and sequencing of this plan. As always, we will attempt to improve upon the dates shown. Periodic updates will be distributed as the project progresses.

Sources

Attached to agenda item: L-1 Tiffin Recreation Center Monthly Report – July 2026

This document's details as JSON

Data last updated October 16, 2026. Built from the archive's documents; see how the data is built.