Tiffin Recreation Center Monthly Report – July 2026 — L-1

Open the PDF

Page 5 of 17

Text from the PDF text layer; check the PDF for anything that matters.
Executive Summary Overview In July, lots of changes occurred. The drywall contractor hung, taped, mudded and sanded all remaining drywall, getting the rest of the rooms ready for painting. The gym equipment arrived and all batting cages, basketball hoops, and curtains were installed. Painters completed main gym area with the exception to the railings on the mezzanine. Electrical contractor started pulling wire and installed overhead gym lights, finishing up lighting in early September. Glazing contractor installed the storefront curtain wall and will be back in August to complete the last curtain wall and interior storefronts. Exterior signs were delivered and installed and will finish in August. Plumbing fixtures and bathroom accessories are in the process of being installed in the locker rooms and shower rooms. Major Milestones / Accomplishments • Gym equipment installation 7/21 • Sign delivery and install 7/10 Upcoming Milestones • Drywall complete (Week of 8/10) • Athletic flooring installation starting late August Key Issues and Concerns • Painting contractor Be authentic, lead with humility, and recognize the needs of others. Care for one another and extend a helping hand wherever it’s needed. Honor our history. Owner Progress Report | 250120 July 2026 Miron Construction Co., Inc. | 5

Sources

Attached to agenda item: L-1 Tiffin Recreation Center Monthly Report – July 2026

This document's details as JSON

Data last updated October 15, 2026. Built from the archive's documents; see how the data is built.