Text from the PDF text layer; check the PDF for anything that matters. Contract Summary
Contract Summary Construction Manager Contingency Summary Owner Contingency Summary
Original Contract Amount: $12,435,142.00 CMaR Contingency Amount: $567,585.00 Owner Contingency Amount: $0.00
Change Orders to Date: -$1,042,001.88 Change Orders to Date: -$220,755.62 Change Orders to Date: $205,560.27
Current Contract Value: $11,393,140.12 CMaR Contingency Value: $346,829.38 Owner Contingency Value: $205,560.27
Current Scope Revisions
CMaR Owner
Allowance Contingency Contingency Estimated Cost
Description Number Date Submitted Status Item? Item? Item? Impact
Project Contingency PCI's June 2025 thru April 2026 001-035 11/30/2025 Approved Yes -$136,877.87
Owner Contingency PCI's June 2025 thru April 2026 001-035 11/30/2025 Approved Yes -$125,040.83
Removal of (4) folding shower seats as shower seats
were provided by Contract 22.00 Plumbing 036 5/5/2026 Approved Yes $815.00
RFI#39: Reroute EF-1 due to dedicated electrical
clearance 037 5/28/2026 Approved Yes -$9,751.75
ASI-17 Add supplemental steel for NW Basketball
Hoop 038 5/29/2026 Approved Yes -$3,322.50
ASI-18 Add Motorized Solar Shades to Windows in
Lower Gym Area 039 5/29/2026 Approved Yes -$17,565.01
RFI#34 Electric Hand Dryers 040 6/8/2026 Approved Yes -$3,634.98
Rework 2nd Floor Fire Main 041 6/8/2026 Approved Yes -$8,737.77
Reconcile Unused Allowances on Concrete Job 042 6/15/2026 Approved Yes $28,447.58
Add Padding to Steel Columns 043 6/16/2026 Approved Yes -$1,174.00
Corner Guards on Portal Frame 044 6/25/2026 Approved Yes -$1,872.02
Destratification Fan Control Wiring 045 7/7/2026 Approved Yes -$11,874.05
Motorized Shade Update 046 7/7/2026 Approved Yes $1,824.00
Add Elevator Vent in Shaft per Code A17.1-3.24.3.1 047 7/21/2026 Approved Yes -$1,590.00
Box out portal frame #2 048 7/8/2026 Approved Yes -$1,858.67
Rework Reception Area Soffit to 9'-0" AFF instead of
7'-2" 049 7/21/2026 Approved Yes -$1,518.89
Add Electrical Power to Operate Backboard Height
Adjustment for Hoops A1, A2, D1 & D2 050 7/21/2026 Approved Yes -$5,014.59
Change out specified badminton/pickleball set (Model
502100) to pickleball set only (Model 502300). 51 8/5/2026 Approved Yes -$2,631.00
Owner Progress Report | 250120 July 2026 Miron Construction Co., Inc. | 10
Sources
- revize: L-1 (HMHfrhcQEul79QQuV1K6O7Vu3vkqUQ.pdf) — where it was found ↗ first seen Oct 12, 2026
Attached to agenda item: L-1 Tiffin Recreation Center Monthly Report – July 2026
Data last updated October 15, 2026. Built from the archive's documents; see how the data is built.