Text read by OCR; check the PDF for anything that matters.Progress Estimate - Lump Sum Work Contractor's Application for Payment
Owner: City of Tiffin Owner's Project No.:
Engineer: MSA Professional Services Engineer's Project No.: 13603016
Contractor: Tricon Construction Group Contractor's Project No.:
Project: Water Treatment Plant Upgrades - City of Tiffin
Contract:
Application No.: 12R Application Period: From 07/24/26 to 08/21/26 Application Date: 08/21/26
56 Grating - Labor $2,777.25 : - 0% 2,777.25
57 - - -
58 Wood, Plastics and Composites . :
59 Structure 10 - Existing Building - - -
60 Walls, Headers, Mezz Hardware - M $15,568.75 - - 0% 15,568.75
61 Walls, Headers, Mezz Hardware - L $45,669.32 - - 0% 45,669.32
62 Trusses - Materials $15,887.00 - - 0% 15,887.00
63 Trusses - Labor $55,229.36 - - 0% 55,229.36
64 Structure 20 - RO Building - - -
65 Walls, Headers, Mezz Hardware - M $25,568.65 9,915.93 9,915.93 39% 15,652.72
66 Walls, Headers, Mezz Hardware - L $55,565.78 16,669.73 16,669.73 30% 38,896.05
67 Trusses - Materials $33,966.50 33,966.50 33,966.50 100% -
68 Trusses - Labor $79,156.72 75,198.88 3,957.84 79,156.72 100% -
69 FRP Grating - Materials $32,000.00 16,000.00 14,400.00 - 30,400.00 95% 1,600.00
70 FRP Grating - Labor $17,836.00 500.00 16,444.20 16,944.20 95% 891.80
71 Structural 30 - Clearwell - - -
72 Walls, Headers, Hardware - Materials $3,692.40 1,846.20 1,846.20 3,692.40 100% -
73 Walls, Headers, Hardware - Labor $18,569.52 9,284.76 9,284.76 18,569.52 100% -
74 Trusses - Materials $5,858.50 5,858.50 5,858.50 100% -
75 Trusses - Labor $16,979.50 16,979.50 16,979.50 100% -
76 - - -
77 Thermal & Moisture Protection - - -
78 Blown Insulation $20,001.00 = - 0% 20,001.00
79 Structure 10 - Existing Building - - -
80 Metal Roofing - Materials $11,566.00 - - 0% 11,566.00
81 Metal Roofing - Labor $6,541.50 - - 0% 6,541.50
82 Preformed Metal Soffit - Materials $1,586.00 - - 0% 1,586.00
83 Preformed Metal Soffit - Labor $1,852.50 - - 0% 1,852.50
84 Gutters & Downspouts - Materials $2,500.00 - - 0% 2,500.00
85 Gutters & Downspouts - Labor $3,215.00 - - 0% 3,215.00
86 Structure 20 - RO Building - - -
EJCDC® C-620 Contractor's Application for Payment
© National Society of Professional Engineers for EJCDC. All rights reserved.
00 62 76-3
of 9 \\fileserver\Shares\Projects\Active\Tiffin WTP (25-012-IA)\3-Tricon\PaymentApplications\Pay Application