Text read by OCR; check the PDF for anything that matters.Progress Estimate - Lump Sum Work Contractor's Application for Payment
Owner: City of Tiffin Owner's Project No.:
Engineer: | MSA Professional Services Engineer's Project No.: 13603016
Contractor: Tricon Construction Group Contractor's Project No.:
Project: Water Treatment Plant Upgrades - City of Tiffin
Contract:
Application No.: 12R Application Period: From 07/24/26 to 08/21/26 Application Date: 08/21/26
87 Metal Roofing - Materials $35,256.00 22,916.40 22,916.40 65% 12,339.60
88 Metal Roofing - Labor $40,587.00 26,381.55 26,381.55 65% 14,205.45
89 Preformed Metal Soffit - Materials $5,877.00 - - 0% 5,877.00
90 Preformed Metal Soffit - Labor $9,992.12 - - 0% 9,992.12
91 Gutters & Downspouts - Materials $5,600.00 - - 0% 5,600.00
92 Gutters & Downspouts - Labor $8,544.32 - - 0% 8,544.32
93 Structure 30 - Clearwell - - -
94 Metal Roofing - Materials $9,442.00 - 944.20 944.20 10% 8,497.80
95 Metal Roofing - Labor $11,566.68 - 1,156.67 1,156.67 10% 10,410.01
96 Preformed Metal Soffit - Materials $3,655.00 - - 0% 3,655.00
97 Preformed Metal Soffit - Labor $6,552.46 - - 0% 6,552.46
98 Gutters & Downspouts - Materials $2,651.00 - - 0% 2,651.00
99 Gutters & Downspouts - Labor $3,215.42 - - 0% 3,215.42
100 Roof Hatches - Materials $6,200.00 6,200.00 6,200.00 100% -
101 = :
102 Openings - - -
103 HM Frames, Doors & Hardware-Materials $53,528.00 - 22,474.24 20,348.16 42 822.40 80% 10,705.60
104 HM Frames, Doors & Hardware-Labor $6,890.00 - 5,512.00 5,512.00 80% 1,378.00
105 Vault Doors - Materials $49,611.00 41,826.00 7,785.00 49,611.00 100% -
106 Vault Doors - Labor $3,110.00 3,110.00 3,110.00 100% -
107 Overhead Door $43,790.00 32,842.50 8,758.00 41,600.50 95% 2,189.50
108 Aluminum Windows $8,996.00 4,700.00 4,700.00 52% 4,296.00
109 - - 5
110 Finishes - - -
111 Resilient Base $2,500.00 - - 0% 2,500.00
112 Epoxy Flooring $67,408.00 - 37,577.75 6,417.25 43,995.00 65% 23,413.00
113 High Performance Coatings $68,724.00 44 381.75 44,381.75 65% 24,342.25
114 - - “
- 7
115 Specialties
116 Signage $450.00 - - 0% 450.00
117 Metal Lockers $7,100.00 - 2,400.00 2,400.00 34% 4,700.00
EJCDC® C-620 Contractor's Application for Payment
© National Society of Professional Engineers for EJCDC. All rights reserved.
00 62 76-4
0f 9 \\fileserver\Shares\Projects\Active\Tiffin WTP (25-012-IA)\3-Tricon\PaymentApplications\Pay Application
Sources
- revize: Agenda packet (packet_2026-09-01_3ad1ee37-4af1-4a67-8983-cc30e19b0f9e.pdf) — where it was found ↗ first seen Oct 12, 2026
Data last updated October 18, 2026. Built from the archive's documents; see how the data is built.