Text read by OCR; check the PDF for anything that matters.Progress Estimate - Lump Sum Work Contractor's Application for Payment
Owner: City of Tiffin Owner's Project No.:
Engineer: MSA Professional Services Engineer's Project No.: 13603016
Contractor: Tricon Construction Group Contractor's Project No.:
Project: Water Treatment Plant Upgrades- City of Tiffin
Contract:
Application No.: 12R Application Period: From 07/24/26 to Application Date: 08/21/26
25 Rebar - Labor $71,872.60 68,278.97 3,593.63 71,872.60 100% -
26 Base Footings Materials $89,665.00 89,665.00 89,665.00 100% -
27 Base Footings Labor $49,315.75 49,315.75 49,315.75 100% -
28 Wall Footings Materials $98,663.00 98,663.00 98,663.00 100% -
29 Wall Footings Labor $54,264.65 54,264.65 54,264.65 100% -
30 Floor Slab Materials $156,442.00 156,442.00 156,442.00 100% -
31 Floor Slab Labor $88,874.50 88,874.50 88,874.50 100% -
32 Equipment Pads Materials $1,515.00 1,363.50 1,363.50 90% 151.50
33 Equipment Pads Labor $3,451.50 3,106.35 3,106.35 90% 345.15
34 Precast Concrete Materials $575,000.00 575,000.00 575,000.00 100% -
35 Precast Concrete Labor $204,412.67 204,412.67 204,412.67 100% -
36 Structure 30- Clearwell - - -
37 Rebar Materials $204,551.00 132,958.15 71,592.85 204,551.00 100% -
38 Rebar labor $112,503.05 73,126.98 39,376.07 112,503.05 100% -
39 Mat Foundation - Materials $123,255.00 123,255.00 123,255.00 100% -
40 Mat Foundation - Labor $68,450.80 68,450.80 68,450.80 100% -
41 Walls - Materials $78,452.00 78,452.00 78,452.00 100% -
42 Walls - Labor $98,065.00 88,258.50 88,258.50 90% 9,806.50
43 Elevated Slab - Materials $198,553.00 198,553.00 198,553.00 100% -
44 Elevated Slab - Labor $109,204.15 109,204.15 109,204.15 100% -
45 Precast Concrete - Materials $210,000.00 202,500.00 202,500.00 96% 7,500.00
46 Precast Concrete - Labor $61,058.33 48,846.67 12,211.67 61,058.34 100% (0.01)
47 = - -
48 Masonry - - -
49 Masonry
- Materials $15,116.00 - 15,116.00 15,116.00 100% -
50 Masonry - Labor $50,603.00 - 50,603.00 50,603.00 100% -
51 7 . =
52 Metals - Z "
53 Metal Fabrications - Materials $57,200.00 - 0% 57,200.00
54 Metal Fabrications - Labor $13,556.25 - - 0% 13,556.25
55 Handrails & Railings Labor $5,966.50 - - 0% 5,966.50
EJCDC® C-620 Contractor's Application for Payment
© National Society of Professional Engineers for EJCDC. All rights reserved.
00 62 76-2
o0f9 \\fileserver\Shares\Projects\Active\Tiffin WTP (25-012-IA)\3-Tricon\PaymentApplications\Pay Application