Text read by OCR; check the PDF for anything that matters.Progress Estimate - Lump Sum Work Contractor's Application for Payment
Owner: City of Tiffin Owner's Project No.:
Engineer: MSA Professional Services Engineer's Project No.: 13603016
Contractor: Tricon Construction Group Contractor's Project No.:
Project: Water Treatment Plant Upgrades- City of Tiffin
Contract:
Application No.: 12R Application Period: From 07/24/26 to 08/21/26 Application Date: 08/21/26
ance to Finish
00 General Requirements
01 General Conditions $588,953.00 429 845.57 78,153.74 507,999.31 86% 80,953.69
02 Bond/Buider's Risk Insurance $199,542.00 199,542.00 199,542.00 100% -
03 Allowance EP1 - Generator & ATS $329,890.00 329,890.00 329,890.00 100% -
04 Allowance EP2 Electrical Equipment Line item 167 - - -
05 Allowance - Electrical Service $5,000.00 - - 0% 5,000.00
06 Mobilization $350,000.00 350,000.00 350,000.00 100% -
07 Site Testing $53,736.00 41,499.99 5,059.16 46,559.15 87% 7,176.85
08 Traffic Control $10,000.00 5,000.00 2,000.00 7,000.00 70% 3,000.00
09 Portable Toilets $5,400.00 2,484.64 1,250.00 3,734.64 69% 1,665.36
10 Dumpster $14,600.00 7,500.00 2,000.00 9,500.00 65% 5,100.00
11 Concrete Washout Pit $2,400.00 1,680.00 240.00 1,920.00 80% 480.00
12 Erosion Control $8,250.00 5,000.00 1,000.00 6,000.00 73% 2,250.00
13 - * =
14 Existing Conditions - - -
15 Structure Demolition $33,445.00 - - 0% 33,445.00
16 - -
17 Concrete - - -
18 Structure 10 - Existing Building - - -
19 Rebar - Materials $54,588.00 49,129.20 49,129.20 90% 5,458.80
20 Rebar - Labor $46,399.80 41,759.82 41,759.82 90% 4,639.98
21 Concrete - Materials $165,884.00 149,295.60 149,295.60 90% 16,588.40
22 Concrete - Labor $91,308.20 82,177.38 82,177.38 90% 9,130.82
23 Structure 20 - RO Building - - -
24 Rebar - Materials $84,556.00 80,328.20 4,227.80 84 556.00 100% -
EJCDC® C-620 Contractor's Application for Payment
© National Society of Professional Engineers for EJCDC. All rights reserved.
00 62 76-10f9 \\fileserver\Shares\Projects\Active\Tiffin WTP (25-012-IA)\3-Tricon\PaymentApplications\Pay Application
Sources
- revize: Agenda packet (packet_2026-09-01_3ad1ee37-4af1-4a67-8983-cc30e19b0f9e.pdf) — where it was found ↗ first seen Oct 12, 2026
Data last updated October 18, 2026. Built from the archive's documents; see how the data is built.