contract agreement · K-2
Discussion and Consideration of Professional Services Agreement with MSA for the Design of Well #6 and Council Action as Needed — K-2
Page 11 of 12
Text from the PDF text layer; check the PDF for anything that matters. ii. Develop design loadings, spatial layout, and connection details for walls
and roofing.
iii. Plan and Cross-Section Drawings and Details of structural construction.
iv. Technical Specifications.
f. Electrical
i. Upgrade of SCADA communication with Wells No. 6 including cost
analysis of fiber, cellular, and radio communication alternatives
ii. Electrical Feeder Sizing Analysis.
iii. Design of Electrical and Controls features for new well, VFD, controls,
lighting, conduit, switches, and receptacles.
iv. Drawings including details and proposed one-line diagrams and P&IDs
for No. Well 6.
v. Technical Specifications.
5. Permitting
MSA will submit the following permits electronically on behalf of the City, with the
fees paid by the City of Tiffin:
a. Iowa Department of Natural Resources (IDNR) Water Supply Construction
Permit Schedules 1a, 1c, 2a, 2b, 6a, 13a, and 14.*
b. Joint Floodplain Permit (no flood study anticipated).*
*Permit review schedule is outside of MSA’s control
6. Cost Estimates
a. MSA shall provide an opinion of probable cost for Well #6 including civil,
mechanical, electrical, plumbing, architectural, structural, controls, contingency,
and engineering.
DELIVERABLES
MSA will provide the following deliverables:
1. Final Plans, Opinion of Probable Cost, and Specifications
a. (1) 11”x17” paper copy of final plans
b. PDF of final plans and specifications
ADDITIONAL SERVICES
Services that are not included in the above Scope of Services can be provided under separate
contract or by amending the scope and fee listed in this Agreement. Examples of additional
services that may be needed or desired for completion of the project include:
1. Review of existing easement documents.
2. Assistance with acquisition of real estate and/or temporary or permanent easements.
3. Survey monumentation.
4. Radiopath Study.
5. Evaluation and accommodations for ADA-compliant spaces.
6. Utility system modeling and/or mapping.
7. Funding applications and administration.
8. Environmental review checklists or exhibits associated with state or federal funding
sources
9. SRF front ends, AIS or BABA specifications
10. Additional meetings not specifically listed in the scope.
Page 9 of 10
(Attachment A: Scope of Services)
G:\13\13603\13603032\Contract\13603032 Tiffin Well #6 Design PSA 9-8-2026.docx
Sources
- revize: K-2 (fppq6CNYks0mOLG5CzwDV1goxVJUXS.pdf) — where it was found ↗ first seen Oct 12, 2026
Attached to agenda item: K-2 Discussion and Consideration of Professional Services Agreement with MSA for the...
Data last updated October 15, 2026. Built from the archive's documents; see how the data is built.