budget
WS - D - Tiffin FS - FY 2023
Page 38 of 48
Text from the PDF text layer; check the PDF for anything that matters. City of Tiffin
Schedule 1
Schedule of Indebtedness
Year Ended June 30, 2023
Amount
Date of Interest Originally
Obligation Issue Rates Issued
General obligation
Corporate Purpose, Series 2017A December 20, 2017 3.00%-3.15% $ 5,140,000
Fire Truck Acquisition, Series 2018A April 4, 2018 4.00% 1,100,000
Corporate Purpose, Series 2019A September 4, 2019 2.00%-2.35% 4,500,000
Urban Renewal and Refunding, Series 2020A August 25, 2020 2.00% 7,670,000
Annual Appropriation Refunding, Series 2021A March 9, 2021 2.00% 2,510,000
Corporate Purpose, Series 2012A May 18, 2022 2.35%-3.15% 2,740,000
Total $ 23,660,000
Revenue notes - direct borrowing
Water Revenue Loan February 6, 2004 1.75% $ 340,000
Sewer Revenue Loan September 30, 2016 1.75% 2,296,000
Sewer Revenue Loan February 5, 2021 0.78% 5,624,000
Sewer Revenue Loan March 4, 2022 0.00% 486,000
Total $ 8,746,000