Text read by the vision model; check the PDF for anything that matters.Assumptions/Exclusions
• Meeting assumed to be held at Tiffin City Hall or at a location deemed necessary by laDOT.
• One public informational meeting is assumed.
• Owner and laDOT will provide list of invitees to meeting.
• Owner will provide location of public informational meeting.
PHASE 800: FINAL DESIGN & LETTING
MSA will develop final plans, specifications, and estimates for the project preferred alternative for the following review milestones by the laDOT.
DM5 - Design Methods Turn-in (100%):
• Prepare final plans, specifications, estimate for submittal to laDOT for review and comment.
D08 – Final Grade & Pave Plans (100%)
• Prepare final plans based on comments received from laDOT at DM5 event, Owner feedback and submit to laDOT for letting.
LO3 – Letting – Combination Grade and Pave
• Bidding will be performed by the laDOT.
• MSA will provide required documentation to laDOT to perform bid & letting services.
• Issue Addenda as appropriate to clarify, correct, or change the bidding documents.
PHASE 900: MEETINGS
• Hold monthly virtual check-in meetings with laDOT District 6 staff to discuss project progress. MSA will coordinate, schedule, and provide meetings minutes for each meeting.
• Concept Plan (30%) review: Attend one meeting with staff during concept plan development and before the concept statement is submitted to the laDOT.
• Preliminary Plan (60%) review: Attend one meeting with staff after preliminary plans are complete, prior to starting check plans.
• Final Plan (100%) review: Attend one meeting with staff after check plans are complete, prior to starting final plans.
Assumptions/Exclusions
• Monthly check-in calls with laDOT will be virtual video conference calls via Microsoft Teams. 24 meetings are assumed over the three year design schedule.
• Design level meetings are assumed to be in person with Owner.