Text from the PDF text layer; check the PDF for anything that matters. City of Tiffin
August 1, 2024
PROJECT UPDATE
MSA has submitted utility information request letters to private utilities located within the corridor on
7/23/24
Comprehensive Water System Evaluation – Clint Wienen
The Preliminary Engineering Report (PER) has been submitted to the DNR for their review and approval.
The DNR requested that a waiver request be submitted for consideration for installing the base slab of the
clearwell below the 100-year flood elevation. The waiver request has been submitted but we have not
received any comments regarding the waiver request or the PER. Doug has reached out the Water Supply
Engineering director and she indicated the review would be completed by the end of July. Approval has
not been provided to date.
Reverse Osmosis Water Treatment Plant Design – Clint Wienen
Bids were received for the procurement of the new generator and ATS and the electrical equipment and
controls. Recommendations of award have been sent to the City. We are nearly finished with the design
but are holding off on the submittal until the DNR provides a response on the variance request that was
submitted for the clearwell.
Pedestrian light (RRFB) on eastern leg of roundabout at Hwy 6 & Park Road. – Andrew Inhelder
City Council approved RRFBs. Shop drawings have been sent to the DOT for review/approval. Vendor and
DOT have been in communication regarding crash worthiness of the RRFB. Awaiting DOT
Review/approval. Contractor to submit an updated schedule to install RRFBs once DOT has approved.
Lead Service Line Inventory. – Andrew Inhelder
MSA and City Staff have worked to identify known water service materials throughout town. MSA is
currently updating a GIS model that the City can use into the future to track service line
material/installation date. Once the model is ready, a report will be exported for submittal.
PROJECT UPDATE