contract agreement · K-3
K-3 - Professional Services Agreement - Recreation Center - Atura Architecture
Page 3 of 9
Text read by the vision model; check the PDF for anything that matters..2 Construction commencement date:
July 2025
.3 Substantial Completion date or dates:
December 2026
.4 Other milestone dates:
§ 1.1.5 The Owner intends to retain a Construction Manager pursuant to the following agreement:
(Indicate agreement type.)
[ X ] AIA Document A133–2019, Standard Form of Agreement Between Owner and Construction Manager as Constructor where the basis of payment is the Cost of the Work Plus a Fee with a Guaranteed Maximum Price.
[ ] AIA Document A134–2019, Standard Form of Agreement Between Owner and Construction Manager as Constructor where the basis of payment is the Cost of the Work Plus a Fee without a Guaranteed Maximum Price.
§ 1.1.6 The Owner’s requirements for accelerated or fast-track design and construction, or phased construction are set forth below:
(List number and type of bid/procurement packages.)
N/A
§ 1.1.7 The Owner’s anticipated Sustainable Objective for the Project:
(Identify and describe the Owner’s Sustainable Objective for the Project, if any.)
None
§ 1.1.7.1 If the Owner identifies a Sustainable Objective, the Owner and Architect shall complete and incorporate AIA Document E234™-2019, Sustainable Projects Exhibit, Construction Manager as Constructor Edition, into this Agreement to define the terms, conditions and services related to the Owner’s Sustainable Objective. If E234-2019 is incorporated into this Agreement, the Owner and Architect shall incorporate the completed E234–2019 into the agreements with the consultants and contractors performing services or Work in any way associated with the Sustainable Objective.
§ 1.1.8 The Owner identifies the following representative in accordance with Section 5.4:
(List name, address, and other contact information.)
Doug Boldt, City Administrator
City of Tiffin
300 Railroad Street
Tiffin, IA 52340
§ 1.1.9 The persons or entities, in addition to the Owner’s representative, who are required to review the Architect’s submittals to the Owner are as follows: