Resolution
Resolution 2017-109
ToAward Bidforthe2017 Wastewater Treatment Plant Phase 2Improvement Project Motion toapprove Resolution 2017-109 – AResolution toAward Bid forthe2017 Wastewater Treatment Plant Phase 2Improvement Project byHavens. Second byBartels. Portsen Construction – won the bidhowever thebids did come 25%over expected. RollCall: Upton, Bartels, Havens, Ryan, Kahler. All ayes, motion carried
adopted · Nov 7, 2017
Timeline
| Date | Step | Recorded in | Motion and votes |
|---|---|---|---|
| Nov 7, 2017 | adopted | minutes meeting 2017-11-07 document |
Motion toapprove Resolution 2017-109 – AResolution toAward Bid forthe2017 Wastewater Treatment Plant Phase 2Improvement Project byHavens moved Havens, seconded Bartels: carried 5 ayes |
| not dated | signed | signed document document a date in its text (2017-11-14) is not the adoption date |
A Resolution to Award Bid for the 2017 Wastewater Treatment Plant Phase 2 Improvement Project |
Documents
Signed copy
- Resolutions-2017-109 (3) 2017-11-14 · laserfiche · PDF
- Resolutions-2017-109 2017-11-14 · laserfiche · PDF
- Resolutions-2017-109 (2) 2017 · laserfiche · PDF
Agendas and minutes citing it
- Minutes-1/17/2017 2017-01-17 · laserfiche · PDF
Data last updated October 15, 2026. Built from the archive's documents; see how the data is built.