contract agreement · K-4
Consideration of Change Order #1 – Tricon Construction Group, Water Treatment Plant Upgrade – Motion to Approve
Page 5 of 7
Text from the PDF text layer; check the PDF for anything that matters.PROJECT: Tiffin, IA WTP Upgrade-Electrical Equipment ASC CO: 20240138-001
Procurement
NAME: COP-001 DATE: May 6, 2025
REFERENCE: Construction Bulletin 1 QUOTATION EXPIRES: 60 Days
CHANGE ORDER PROPOSAL
Changes to the System Integrator Procurement Contract Documents.
Control Panel Modifications
A One(1) 10-SCC-1 Supervisory Control Center Modifications, as required per Construction Bulletin 1, in accordance with
Section 26 90 10, and modified as detailed below.
Proposed panel modifications shall be complete with addition of Allen Bradley CompactLogix I/O cards to allow for addition of
Fluoride chemical system, additional flow metering, and interface relays, fuses, terminals, and wireway as needed.
B One (1) 20-SCC-1 Supervisory Control Center Modifications, as required per Construction Bulletin 1, in accordance with
Section 26 90 10, and modified as detailed below.
Proposed panel modifications shall be complete with addition of I/O for Well 4 level transducer, PLC programming, removal of
ERMS Switch, and interface relays, fuses, terminals, and wireway as needed.
Instrumentation and Filed Devices
C Minus One (-1) Float Switch as required per Section 26 90 20, 2.06 and as detailed below.
1. LSH-1-4-2, Manhole #4 High Water Level Alarm - Deleted.
Motor Control Equipment Modifications
D One (1) 20-MCC-1A Modifications, as required per Construction Bulletin 1, in accordance with Section 26 24 19 and as
detailed below.
1 of 3
Sources
- revize: Attachment (3R1W5VEOEnpDNmpsjgVCBtNRV1vLLn.pdf) — where it was found ↗ first seen Oct 12, 2026
- sharepoint (K-4 - Change Order 1 - Tricon - Water Treatment Plant.pdf) — where it was found ↗ first seen Oct 12, 2026
Attached to agenda item: K-4 Consideration of Change Order #1 – Tricon Construction Group, Water Treatment Plant...
Data last updated October 15, 2026. Built from the archive's documents; see how the data is built.