City of Tiffin August 28, 2025 PROJECT UPDATE NORTH PARK ROAD IMPROVEMENTS – JAMES WATTERS As of August 25th, 2025, the south section of North Park Road including the new roundabout at the Tiffin/Oak Hill Elementary School bus loop is open to traffic. Some work in this section is still being completed but is expected to be finished by the end of the month. The section of roadway between the roundabout and the main entrance of Oak Hill Elementary will remain closed until all construction activities are completed. Remaining tasks include median pavement, sign installation, pavement markings, roadway lighting installation, and seeding work. Once these items are finished, Boomerang construction personnel are expected to leave the site. The reopening of this portion of the road is anticipated between mid-September and mid-October 2025. Following the conclusion of the 2025 construction season, North Park Road is expected to be open to two-way traffic for the remainder of the year until construction resumes in the Spring of 2026. The majority of sidewalk/trail and the pedestrian underpass will not be available for public use following the opening of North Park Road for this fall. Much of the sidewalk/trail is not yet constructed or does not connect with other proposed or existing facilities. An on-site safety meeting was held on August 8th to discuss conditions required for opening of the road to the public as well as site safety and security concerns. Representatives from the City of Tiffin, MSA, CCACSD, the Johnson County Sheriff’s Office, and Boomerang were present. The following week on August 14th, CCACSD staff were briefed on traffic control expected to be in place for the “Back to School” events and for the start of classes. VILLAGE DRIVE & ROBERTS FERRY ROAD SIGNAL DESIGN – CHAD WAGNER Traffic counts at this intersection are being scheduled along with survey. A kickoff meeting will be scheduled with City staff to discuss project once traffic counts are collected. PROJECT UPDATE Page 2 of 5

Sources

  • revize: Engineer's Report (R8CRh86URsE8x6z6xZEcWotvNwT4dx.pdf) — where it was found ↗ first seen Oct 12, 2026
  • sharepoint (M-9 - Staff Cover - Engineer's Report.pdf) — where it was found ↗ first seen Oct 12, 2026

Attached to agenda item: M Reports from City Personnel

This document's details as JSON

Data last updated October 15, 2026. Built from the archive's documents; see how the data is built.