Text from the PDF text layer; check the PDF for anything that matters.Construction Summary
Schedule Update
July did not see much action other than dirt settling. We did get good news that the surcharge is complete and has
been removed. Coming up in August we are looking to get rest of the contractors established, all bought into a
schedule and progress being made. There still will be a few more weeks of little to no action as Bid Package 2 is
being finalized and contracts released.
Delays
• Weather – See Daily Log Weather Report
‒ We had 0 rain days
Weather Delays (Sitework) Weather Delays (Construction)
Scheduled Occurred Left Scheduled Occurred Left
6 2 0 19 0 0
• Materials & Labor
‒ None at this time
Key Issues / Concerns & Recommended Action Steps
• Finalizing our baseline schedule from the input of our trade partners
• With surcharge complete, Sitework Weather Delay will be reduced to 0 days left
• Keeping up on erosion control and cleaning up and debris on South Park Rd.
Deliver unmatched quality,
create meaningful
connections, and craft
unforgettable experiences in
everything we do. Capture
what truly matters and find
ways to inspire.
Owner Progress Report | 250120 August 2025 Miron Construction Co., Inc.
|8
Sources
- revize: Attachment (v9PaS6A2oWkWF59ibVczjSuzrOcrMO.pdf) — where it was found ↗ first seen Oct 12, 2026
- sharepoint (L-2 - Miron - Project Update.pdf) — where it was found ↗ first seen Oct 12, 2026
Attached to agenda item: Miron - Project Update - Tiffin Recreation Center
Data last updated October 15, 2026. Built from the archive's documents; see how the data is built.