staff report memo · L-2

Miron - Project Update - Tiffin Recreation Center

Dated September 16, 2025City Council — regular meeting, September 16, 2025 19 pages

Open the PDF

Page 16 of 19

Text from the PDF text layer; check the PDF for anything that matters.
Tiffin Community Recreation Center Layout Name: 250120B Construction Schedule Update 09/05/2025 Miron Construction Co., Inc. Data Date: 05-Sep-25 Page 3 of 6 250120-15PM 20250905 Activity ID Resp PredecessorsSuccessors Activity Name Orig Rem Start Finish 2025 2026 Dur Dur Nov Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct 2540 MIRON CONC 1350 2550, Form and Pour Footings - Sequence 2 (Teal) 4 4 29-Sep-25 02-Oct-25 2630 2570 MIRON CONC 1350 2620, Form and Pour Footings - Sequence 1A & 1B Elevator (Brown) 5 5 29-Sep-25 03-Oct-25 2610, 2610 MIRON CONC 2570 2600 2700 Form and Pour Footings - Sequence 1C (Orange) 2 2 01-Oct-25 02-Oct-25 2550 MIRON CONC 2540 2560, Form and Pour Footings - Sequence 3 (Light Orange) 4 4 03-Oct-25 08-Oct-25 2640 2600 MIRON CONC 2570 2690 Form and Pour Footings - Sequence 1D (Purple) 2 2 03-Oct-25 06-Oct-25 2700 MIRON CONC 2610 2740 Form/Pour/Strip Foundation Walls - Sequence 2 (Interior 3 3 03-Oct-25 07-Oct-25 Orange) 2620 MIRON CONC 2570, 2730, Form/Pour/Strip Foundation Walls - Sequence 1 Elevator 5 5 06-Oct-25 10-Oct-25 2360 2630 (Brown) 2690 MIRON CONC 2600 2740 Form/Pour/Strip Foundation Walls - Sequence 3 (Purple) 4 4 07-Oct-25 10-Oct-25 2560 MIRON CONC 2550 2580, Form and Pour Footings - Sequence 4 (Teal) 4 4 09-Oct-25 14-Oct-25 2650 2630 MIRON CONC 2540, 2640, Form/Pour/Strip Foundation Walls - Sequence 4 (Teal) 4 4 13-Oct-25 16-Oct-25 2620 2740 2580 MIRON CONC 2560 2590, Form and Pour Footings - Sequence 5 (Green) 4 4 15-Oct-25 20-Oct-25 2660 2640 MIRON CONC 2550, 2750, Form/Pour/Strip Foundation Walls - Sequence 5 (Light Orange) 4 4 17-Oct-25 22-Oct-25 2630 2650 2730 CORRIDORCOAT 2620 2740 Elevator Shaft Waterproofing 1 1 20-Oct-25 20-Oct-25 2740 SCHRADER 2730, 2070, Backfill Foundation Sequence 1,2,3,4 2 2 21-Oct-25 22-Oct-25 2700, 1380 1380 AAAMECH 2630, 2740 2800 Plumbing Underground 10 10 23-Oct-25 05-Nov-25 2070 SEEHASE 2740 2100 Elevator Shaft 5 5 23-Oct-25 29-Oct-25 2650 MIRON CONC 2560, 2660, Form/Pour/Strip Foundation Walls - Sequence 6 (Orange) 4 4 23-Oct-25 28-Oct-25 2640 2750 2660 MIRON CONC 2580, 2760, Form/Pour/Strip Foundation Walls - Sequence 7 (Pink) 4 4 29-Oct-25 03-Nov-25 2650 2670 2750 SCHRADER 2640, 1370, Backfill Foundation Sequence 5 & 6 2 2 29-Oct-25 30-Oct-25 2650 2810, 2100 SEEHASE 2070 2710, First Course CMU Bearing Walls 3 3 30-Oct-25 03-Nov-25 2810 SCHRADER 2750 2590 Excavate Foundations (Footings Sequence 6) 1 1 31-Oct-25 31-Oct-25 2590 MIRON CONC 2580, 2680, Form and Pour Footings - Sequence 6 (Yellow) 3 3 03-Nov-25 05-Nov-25 2810 2710 2670 MIRON CONC 2660 2760 Form/Pour/Strip Foundation Walls - Sequence 8 (Green) 4 4 04-Nov-25 07-Nov-25 2680 MIRON CONC 2590 2770 Form/Pour/Strip Foundation Walls - Sequence 9 (Yellow) 4 4 06-Nov-25 11-Nov-25 2710 MIRON CONC 2590, 2790, Form/Pour/Strip Foundation Walls - Sequence 10 (East Stoop 3 3 06-Nov-25 10-Nov-25 2750 2720 and Mechancial Pad) 2800 SCHRADER 1380 2820 Rock Base Course - Locker Room 1 1 06-Nov-25 06-Nov-25 2820 MIRON CONC 2800 2000, Prep/Pour Locker Room 2 2 07-Nov-25 10-Nov-25 1470 2760 SCHRADER 2660, 1370 Backfill Foundation Sequence 7 & 8 2 2 10-Nov-25 11-Nov-25 2670 2720 MIRON CONC 2710, 2790 Form/Pour/Strip Foundation Walls - Sequence 11 (South Stoop 5 5 11-Nov-25 17-Nov-25 2750 and Mechancial Pads) 1460 SCHRADER 2770 1370 Rock Base Course 5 5 12-Nov-25 18-Nov-25 2770 SCHRADER 2680 1460, Backfill Foundation Sequence 9 (Yellow) 2 2 12-Nov-25 13-Nov-25 1370 2790 SCHRADER 2710, 1590 Backfill and Subgrade Sequence 10 & 11 3 3 18-Nov-25 20-Nov-25 2720 Actual Work Please review the activities for which you are responsible and the relationships to the activities of other Remaining Work trades. If you have questions or comments, please contact Patrick Myers & Corey Boyles immediately. If Critical Remaining Work we receive no comments from you by 5 workings days, we will assume a lack of response to be your Milestone agreement and commitment to the durations, relationships, and sequencing of this plan. As always, we will attempt to improve upon the dates shown. Periodic updates will be distributed as the project progresses.

Sources

Attached to agenda item: Miron - Project Update - Tiffin Recreation Center

This document's details as JSON

Data last updated October 15, 2026. Built from the archive's documents; see how the data is built.