Miron - Project Update - Tiffin Recreation Center
Page 14 of 19
Text from the PDF text layer; check the PDF for anything that matters. Tiffin Community Recreation Center Layout Name: 250120B
Construction Schedule Update 09/05/2025
Miron Construction Co., Inc. Data Date: 05-Sep-25
Page 1 of 6
250120-15PM 20250905
Activity ID Resp PredecessorsSuccessors Activity Name Orig Rem Start Finish 2025 2026
Dur Dur Nov
Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct
Tiffin Community Recreation Center 375 301 22-May-25 A 10-Nov-26
PRECONSTRUCTION 0 0
PRECONSTRUCTION - BP1 0 0
PRECONSTRUCTION - BP2 0 0
SUBMITTALS 104 15 22-May-25 A 26-Sep-25
1140 MERIT 1050 1240, PEMB - Final Design & Submittal 40 15 22-May-25 A 26-Sep-25
1190
1900 ILTENS 1120 1910 Roof Top Units - Submittal 30 15 18-Aug-25 A 26-Sep-25
2060 PRICEELEC 1120 1510 Electrical Gear - Submittal 15 10 18-Aug-25 A 19-Sep-25
2140 TSF 1120 2210 Steel - Sequence 3 High Steel Submittal 10 5 18-Aug-25 A 12-Sep-25
2150 TSF 1120 2220 Steel - Sequence 4 GL2 thru GL5 Submittal 15 5 18-Aug-25 A 12-Sep-25
2160 TSF 1120 2230 Steel - Sequence 5 GL5 thru GL11/Track Submittal 15 5 18-Aug-25 A 12-Sep-25
2170 TSF 1120 2240 Steel - Sequence 6 Main Stair Submittal 20 1 18-Aug-25 A 08-Sep-25
2180 TSF 1120 2250 Steel - Sequence 7 Running Track Stair Submittal 20 1 18-Aug-25 A 08-Sep-25
2190 TSF 1120 2260 Steel - Sequence 8 Running Track Railing Submit tal 30 5 18-Aug-25 A 12-Sep-25
2200 TSF 1120 2270 Steel - Sequence 9 Mechanical Screen Submittal 40 5 18-Aug-25 A 12-Sep-25
2490 ZEPHYR 1120 2500 Curtain Wall/Aluminum Entrance/Glazing Submittal 15 6 18-Aug-25 A 15-Sep-25
A/E REVIEW / APPROVAL 27 25 29-Aug-25 A 10-Oct-25
1310 A/E 2050 1500 Rebar Shop Drawing - Submittal Review 10 2 29-Aug-25 A 09-Sep-25
1920 A/E 1710 1930 Steel - Sequence 2 Embed Submittal Review 10 7 02-Sep-25 A 16-Sep-25
2280 TSF 2130 2360 Steel - Sequence 1 Anchor Bolts Submittal Review 10 7 02-Sep-25 A 16-Sep-25
1230 A/E 1180 1280 Aggregate Piers - Submittal Review 10 3 05-Sep-25 A 10-Sep-25
2240 TSF 2170 2320 Steel - Sequence 6 Main Stair Submittal Review 10 10 09-Sep-25 22-Sep-25
2250 TSF 2180 2330 Steel - Sequence 7 Running Track Stair Submittal Review 10 10 09-Sep-25 22-Sep-25
2210 TSF 2140 2290 Steel - Sequence 3 High Steel Submittal Review 10 10 15-Sep-25 26-Sep-25
2220 TSF 2150 2300 Steel - Sequence 4 GL2 thru GL5 Submittal Review 10 10 15-Sep-25 26-Sep-25
2230 TSF 2160 2310 Steel - Sequence 5 GL5 thru GL11/Track Submittal Review 10 10 15-Sep-25 26-Sep-25
2260 TSF 2190 2340 Steel - Sequence 8 Running Track Railing Submit tal Revie w 10 10 15-Sep-25 26-Sep-25
2270 TSF 2200 2350 Steel - Sequence 9 Mechanical Screen Submittal Review 10 10 15-Sep-25 26-Sep-25
2500 ZEPHYR 2490 2510, Curtain Wall/Aluminum Entrance/Glazing Submittal Review 10 10 16-Sep-25 29-Sep-25
2530
1510 A/E 2060 1650 Electrical Gear - Submittal Review 10 10 22-Sep-25 03-Oct-25
1190 A/E 1140 1240 PEMB - Final Design Submittal Review 10 10 29-Sep-25 10-Oct-25
1910 A/E 1900 1690 Roof Top Units - Submittal Review 10 10 29-Sep-25 10-Oct-25
Actual Work Please review the activities for which you are responsible and the relationships to the activities of other
Remaining Work trades. If you have questions or comments, please contact Patrick Myers & Corey Boyles immediately. If
Critical Remaining Work we receive no comments from you by 5 workings days, we will assume a lack of response to be your
Milestone agreement and commitment to the durations, relationships, and sequencing of this plan. As always, we will
attempt to improve upon the dates shown. Periodic updates will be distributed as the project progresses.
Sources
- revize: Attachment (v9PaS6A2oWkWF59ibVczjSuzrOcrMO.pdf) — where it was found ↗ first seen Oct 12, 2026
- sharepoint (L-2 - Miron - Project Update.pdf) — where it was found ↗ first seen Oct 12, 2026