Miron - Project Update - Tiffin Recreation Center
Page 11 of 19
Text from the PDF text layer; check the PDF for anything that matters. Contract Summary
Contract Summary Contingency Summary
Original Contract Amount: $12,435,142.00 Original Contract Amount: $567,585.00
Change Orders to Date: $0.00 Change Orders to Date: $2,699.80
Current Contract Value: $12,435,142.00 Current Contract Value: $570,284.80
Current Scope Revisions
Date Allowance Contingency Estimated
Description Number Submitted Status Item? Item? Cost Impact
100% IFC Set - Civil BP1 (Add Fire Protection
Line) 001 6/16/2025 Approved Yes Yes $7,300.12
ASI-01 Civil Utility Information 002 7/3/2025 Approved $0.00
Bid Package #2 Bid Documents and Drawing
Updates 003 9/8/2025 In Review $0.00
Finalize Contract Budgets from Bid Package #2 004 8/21/2025 Approved $0.00
BP #2 Contract Reconciliation 005 In Review -$1,042,000.00
ASI-02 Transformer Pad, Changes Related to
PEMB, Changes Related to Elevator 006 Collecting Pricing
Owner Progress Report | 250120 August 2025 Miron Construction Co., Inc.
| 10
Sources
- revize: Attachment (v9PaS6A2oWkWF59ibVczjSuzrOcrMO.pdf) — where it was found ↗ first seen Oct 12, 2026
- sharepoint (L-2 - Miron - Project Update.pdf) — where it was found ↗ first seen Oct 12, 2026
Attached to agenda item: Miron - Project Update - Tiffin Recreation Center
Data last updated October 15, 2026. Built from the archive's documents; see how the data is built.