staff report memo · L-3
Tiffin Recreation Center Monthly Report
Page 6 of 19
Text from the PDF text layer; check the PDF for anything that matters.Design/Action Items
Accomplishments
• Released updated drawings to reflect city and fire marshal's comments
• Finalized finish colors and selections with finish schedule
Upcoming Submittals/Design Deliverables
• Submission of fire alarm shop drawings
• Submission of fire protection shop drawings
Submittals
• None overdue
• Slab on grade
Requests for Information
• 12 Total RFI’s
• 5 RFI’s this month
• 0 Pending answers
‒ 0 over due
Areas of Concern / Focus
• Incorporating drawing comments into construction
Get involved, respond with
urgency, and work as a team
to get the job done. Leverage
the strengths of each
individual and overcome
obstacles as one.
Owner Progress Report | 250120 October 2025 Miron Construction Co., Inc.
|6
Sources
- revize: Attachment (GUStiweSiMHBuDC7PDhsDsVSgrKkbF.pdf) — where it was found ↗ first seen Oct 12, 2026
- sharepoint (L-3 - Tiffin Recreation Center Monthly Report - October 2025.pdf) — where it was found ↗ first seen Oct 12, 2026
Attached to agenda item: L-3 Tiffin Recreation Center Monthly Report
Data last updated October 16, 2026. Built from the archive's documents; see how the data is built.