Tiffin Recreation Center Monthly Report
Page 5 of 19
Text from the PDF text layer; check the PDF for anything that matters.Executive Summary
Overview
Happy Fall! In October we were able to get 95% of the foundation footings and walls poured. With foundation walls,
the building footprint is starting to take shape. Seehase Masonry was also able to start on the elevator shaft, which
will be completed in the first week of November. We did experience our first weather delay with some rain we had. We
wrap up foundation work in early November. In November the building will take shape as the erection for the building
will begin. Underground work will also begin in November.
Major Milestones / Accomplishments
• Started elevator shaft
• Accounted for city and fire marshal’s comments from drawing review
Upcoming Milestones
• Start erecting the Pre-Engineered Metal Building (PEMB)
• Complete foundation walls and continue pouring stoops and stoop topping slabs
• Start plumbing and electrical underground
• Building enclosure – End of January 2026
Key Issues and Concerns
• Applying for utility applications to begin coordinating with utility companies
‒ Electrical (Linn County REC), coordination has begun and building transformer is at their lot
‒ Gas (MidAmercian Energy), design is complete and payment was sent out
• Weather and building enclosure to pour slabs on grades
Be authentic, lead with
humility, and recognize the
needs of others. Care for one
another and extend a helping
hand wherever it’s needed.
Honor our history.
Owner Progress Report | 250120 October 2025 Miron Construction Co., Inc.
|5
Sources
- revize: Attachment (GUStiweSiMHBuDC7PDhsDsVSgrKkbF.pdf) — where it was found ↗ first seen Oct 12, 2026
- sharepoint (L-3 - Tiffin Recreation Center Monthly Report - October 2025.pdf) — where it was found ↗ first seen Oct 12, 2026
Attached to agenda item: L-3 Tiffin Recreation Center Monthly Report
Data last updated October 16, 2026. Built from the archive's documents; see how the data is built.