Text from the PDF text layer; check the PDF for anything that matters. Tiffin Community Recreation Center Layout Name: 250120B
Construction Schedule Update 11/07/2025
Miron Construction Co., Inc. Data Date: 07-Nov-25
Page 1 of 5
250120-23PM 20251107
Activity ID Resp PredecessorsSuccessors Activity Name Orig Rem Start Finish 2025 2026
Dur Dur
Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct ov
Tiffin Community Recreation Center 310 247 12-Aug-25 A 28-Oct-26
PRECONSTRUCTION 0 0
PRECONSTRUCTION - BP1 0 0
PRECONSTRUCTION - BP2 0 0
SUBMITTALS 10 0 30-Oct-25 A 04-Nov-25 A
A1000 ZEPHYR 2500 3070 Curtain Wall/Aluminume Entrance/Glazing Submittal Rev 1. 10 0 30-Oct-25 A 04-Nov-25 A
A/E REVIEW / APPROVAL 0 0
FAB / DELIVER 174 87 12-Aug-25 A 13-Mar-26
1270 OTIS 1220 1830 Elevator - Fab and Deliver 70 17 12-Aug-25 A 03-Dec-25
2980 MIRON DOOR 2970 1520, Hollow Metal Frames Fab and Deliver 45 45 30-Sep-25 A 14-Jan-26
1550
2990 MIRON DOOR 2970 2920 Hollow Metal Doors Fab and Deliver 60 36 30-Sep-25 A 31-Dec-25
3000 MIRON DOOR 2970 2920 Wood Doors & Hardware Fab and Deliver 70 46 30-Sep-25 A 15-Jan-26
2290 TSF 2210 2370, Steel - Sequence 3 High Steel Fab and Deliver 50 20 03-Oct-25 A 08-Dec-25
2380
2300 TSF 2220 2380 Steel - Sequence 4 GL2 thru GL5 Fab and Deliver 73 43 03-Oct-25 A 12-Jan-26
2310 TSF 2230 2390 Steel - Sequence 5 GL5 thru GL11/Track Fab and Deliver 83 53 03-Oct-25 A 26-Jan-26
1650 MEP 1510 2010 Electrical Gear - Fab and Delivery 70 50 13-Oct-25 A 21-Jan-26
1690 MEP 1910 2850 RTU - Fab and Delivery 60 50 13-Oct-25 A 21-Jan-26
2320 TSF 2240 2400 Steel - Sequence 6 Main Stair Fab and Deliver 106 72 20-Oct-25 A 20-Feb-26
2330 TSF 2250 2410 Steel - Sequence 7 Running Track Stair Fab and Deliver 111 77 20-Oct-25 A 27-Feb-26
2340 TSF 2260 2420 Steel - Sequence 8 Running Track Railing Fab and Deliver 107 77 28-Oct-25 A 27-Feb-26
2350 TSF 2270 2430 Steel - Sequence 9 Mechanical Screen Fab and Deliver 117 87 28-Oct-25 A 13-Mar-26
1250 FREEMAN 1200 1340 Site Utilities - Fab and Deliver 10 0 03-Nov-25 A 07-Nov-25 A
2530 ZEPHYR 3070, 1840 Curtain Wall/Aluminum Entrance/Glazing Fab and Deliver (Hold 45 45 10-Nov-25 14-Jan-26
2500 RO Openings)
2510 ZEPHYR 3070, 1840 Curtain Wall/Aluminum Entrance/Glazing Fab and Deliver (Field 15 15 02-Feb-26 20-Feb-26
2500, Verif ication Openings)
SITEWORK 2520 217 208 28-Oct-25 A 03-Sep-26
1340 FREEMAN 1250, 1960 Site Utilities - Storm Outlets 5 3 28-Oct-25 A 19-Nov-25
1420
1420 FREEMAN 1350 1340 Site Utilites - Parking Lot to Riser 5 5 10-Nov-25 14-Nov-25
2120 SCHRADER 1830 1940 Rough Grade 5 5 30-Apr-26 06-May-26
1940 ALL AMERICAN 1840, 1960, Site Concrete - Curbs and Sidewalks 8 8 07-May-26 18-May-26
2120 1950
1960 SCHRADER 1940, 1870 Final Grade 5 5 19-May-26 26-May-26
1340,
1870 CULVERS 2430
1960, 1760 Landscape 10 10 27-May-26 09-Jun-26
1440
1950 LLPELL 1940, 1760 Asphalt Overlay and Parking Lot Striping 5 5 27-Aug-26 03-Sep-26
1720
Actual Work
Remaining Work Please review the activities for which you are responsible and the relationships to the activities of other
Critical Remaining Work trades. If you have questions or comments, please contact Patrick Myers & Corey Boyles immediately. If
Milestone we receive no comments from you by 5 workings days, we will assume a lack of response to be your
agreement and commitment to the durations, relationships, and sequencing of this plan. As always, we will
attempt to improve upon the dates shown. Periodic updates will be distributed as the project progresses.
Sources
- revize: Attachment (GUStiweSiMHBuDC7PDhsDsVSgrKkbF.pdf) — where it was found ↗ first seen Oct 12, 2026
- sharepoint (L-3 - Tiffin Recreation Center Monthly Report - October 2025.pdf) — where it was found ↗ first seen Oct 12, 2026
Attached to agenda item: L-3 Tiffin Recreation Center Monthly Report
Data last updated October 16, 2026. Built from the archive's documents; see how the data is built.