Tiffin Recreation Center Monthly Report
Page 17 of 19
Text from the PDF text layer; check the PDF for anything that matters. Tiffin Community Recreation Center Layout Name: 250120B
Construction Schedule Update 11/07/2025
Miron Construction Co., Inc. Data Date: 07-Nov-25
Page 4 of 5
250120-23PM 20251107
Activity ID Resp PredecessorsSuccessors Activity Name Orig Rem Start Finish 2025 2026
Dur Dur
Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct ov
1600 PEARSON 1530, 1610 1st Floor Drywall - Hang 10 10 13-Apr-26 24-Apr-26
1840
2890 PRICEELEC 1680, 1760 2nd Floor - Electrical Trim and Lights 10 10 13-Apr-26 24-Apr-26
1990
2900 ILTENS 1680 1820 2nd Floor - Fabric Duct and Diffusers 8 8 13-Apr-26 22-Apr-26
2910 H2I 1680 1720 Gym Equipment - Installation 20 20 13-Apr-26 08-May-26
1700 AAAMECH 1680, 2090 2nd Floor Plumbing Fixtures 5 5 15-Apr-26 21-Apr-26
3010
1610 PEARSON 1600 1620 1st Floor Drywall - Tape and Sand 15 15 27-Apr-26 15-May-26
1620 YOUNGS 1610, 1630, 1st Floor Paint 8 8 18-May-26 28-May-26
1470 1730,
3020 APPLEBY 1620 1720,
1640 1st Floor Wall Tile 15 15 21-May-26 11-Jun-26
1630 HARGERS 1620, 1640, 1st Floor Ceiling Tile - Grid 15 15 29-May-26 18-Jun-26
2940 1740,
2870 PRICEELEC 1620, 2880,
1760 1st Floor - Electrical Trim and Lig hts 10 10 05-Jun-26 18-Jun-26
1630
2880 ILTENS 1630 1820 1st Floor - Diffusers 10 10 05-Jun-26 18-Jun-26
1640 AAAMECH 1630, 1650, 1st Floor Plumbing Fixtures 5 5 19-Jun-26 25-Jun-26
3020 2090
1650 CEILING 1640 1820 1st Floor Ceiling Tile - Drop 2 2 26-Jun-26 29-Jun-26
2090 ILTENS 1640, 1720, HVAC Startup 3 3 26-Jun-26 30-Jun-26
1700 1820,
1730 PHILLIPSFLR 1620, 1810,
1760 Flooring - Turf Area 10 10 01-Jul-26 15-Jul-26
2090
1740 APPLEBY 1630, 2080, Soft Goods Flooring - 1st Floor 10 10 01-Jul-26 15-Jul-26
1830, 2920
1810 PHILLIPSFLR 2090
2090 1760 Athletic Flooring - 2nd Floor 15 15 01-Jul-26 22-Jul-26
2080 GENTRADES 1620, 1760 Architectural Casework Install 15 15 01-Jul-26 22-Jul-26
1680,
2860 PHILLIPSFLR 1740
2090 1720 Athletic Flooring - 1st Floor 10 10 01-Jul-26 15-Jul-26
1720 H2I 1970, 1820, Wood Flooring - Gym Area 30 30 16-Jul-26 26-Aug-26
1620, 1950
2920 MIRON DOOR 2090,
1740, 1820 Interior Door and Harware Installation 5 5 16-Jul-26 22-Jul-26
2990,
1820 MEP 3000
1720, 1760, Test & Balance 9 9 27-Aug-26 09-Sep-26
1650, 1880
1880 MEP 2090,
1820 1760 Commissioning 9 9 10-Sep-26 22-Sep-26
WEATHER CONTINGENCY 242 242 10-Nov-25 21-Oct-26
WEATHER CONTINGENCY SITE WORK BP1 4 4 10-Nov-25 13-Nov-25
1750 MIRON 2040 Weather Contingency Sitework (May '25-July'25 6 Days) 4 4 10-Nov-25 13-Nov-25
CRITICAL 0 0
NON-CRITICAL 0 0
WEATHER CONTINGENCY CONSTRUCTION BP2 11 11 07-Oct-26 21-Oct-26
1890 MIRON 1770 1780 Weather Contingency Construction (Sept '25-Jan '26 12 Days) 11 11 07-Oct-26 21-Oct-26
CRITICAL 0 0
NON-CRITICAL 0 0
Actual Work
Remaining Work Please review the activities for which you are responsible and the relationships to the activities of other
Critical Remaining Work trades. If you have questions or comments, please contact Patrick Myers & Corey Boyles immediately. If
Milestone we receive no comments from you by 5 workings days, we will assume a lack of response to be your
agreement and commitment to the durations, relationships, and sequencing of this plan. As always, we will
attempt to improve upon the dates shown. Periodic updates will be distributed as the project progresses.
Sources
- revize: Attachment (GUStiweSiMHBuDC7PDhsDsVSgrKkbF.pdf) — where it was found ↗ first seen Oct 12, 2026
- sharepoint (L-3 - Tiffin Recreation Center Monthly Report - October 2025.pdf) — where it was found ↗ first seen Oct 12, 2026
Attached to agenda item: L-3 Tiffin Recreation Center Monthly Report
Data last updated October 16, 2026. Built from the archive's documents; see how the data is built.