Tiffin Recreation Center Monthly Report
Page 16 of 19
Text from the PDF text layer; check the PDF for anything that matters. Tiffin Community Recreation Center Layout Name: 250120B
Construction Schedule Update 11/07/2025
Miron Construction Co., Inc. Data Date: 07-Nov-25
Page 3 of 5
250120-23PM 20251107
Activity ID Resp PredecessorsSuccessors Activity Name Orig Rem Start Finish 2025 2026
Dur Dur
Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct ov
2480 TSF 2470 2400, Steel - Sequence 5 Decking 4 4 04-Feb-26 09-Feb-26
2950
2390 TSF 2310, 2460 Steel - Sequence 5 Track Rods 2 2 05-Feb-26 06-Feb-26
2450,
1430 MIRON CONC 2370
2450, 1550, Prep/Pour/Strip 2nd Floor to GL 5 5 5 13-Feb-26 19-Feb-26
2780 1570,
1410 MIRON 1840,
1390 Preinstall - Gym Floor and Slab on Grade 0 0 20-Feb-26
2950 MIRON CONC 1430, 1980 Prep/Pour/Strip 2nd Floor Sequence 2A 3 3 20-Feb-26 24-Feb-26
2480
2400 TSF 2480, 2410 Steel - Sequence 6 Main Stair Install/Detail 5 5 23-Feb-26 27-Feb-26
2320
1980 MIRON CONC 2950 1390, Prep/Pour/Strip 2nd Floor Sequence 2B 2 2 25-Feb-26 26-Feb-26
2930
1390 MIRON CONC 1450, 1970, Prep/Pour/Strip Slab on Grade - Gym Floor (Orange) 5 5 27-Feb-26 05-Mar-26
2780, 1360,
1550 PEARSON 1980,
1430, 1580
1560 2nd Floor Interior Steel Stud Framing 5 5 27-Feb-26 05-Mar-26
2980
1570 AAAMECH 1430 1560, 2nd Floor Overhead Rough In - MEP 8 8 27-Feb-26 10-Mar-26
1580
1840 GLAZING 1430, 1600, Glazing 15 15 27-Feb-26 19-Mar-26
2510, 1940
2930 TRI CITY FP 2530
1980 1680 2nd Floor Fire Protection 15 15 27-Feb-26 19-Mar-26
1970 MIRON 1390 1720 Gym Floor Moisture Mitigation 40 40 06-Mar-26 30-Apr-26
1360 MIRON CONC 1390 2840, Prep/Pour/Strip Slab on Grade - Pink 3 3 06-Mar-26 10-Mar-26
1520,
2420 TSF 2410, 1540
1680 Steel - Sequence 8 Running Track Railing Instal 7 7 10-Mar-26 18-Mar-26
2340
1560 AAAMECH 1550, 1660 2nd Floor In Wall Rough In - MEP 5 5 11-Mar-26 17-Mar-26
1570
1580 AAAMECH 1570, 1680 Gym Area Overhead Rough In - MEP 15 15 11-Mar-26 31-Mar-26
1390
2840 MIRON CONC 1360 2830, Prep/Pour/Strip Slab on Grade - Green 3 3 11-Mar-26 13-Mar-26
2940
2430 TSF 2850, 1960 Steel - Sequence 9 Mechanical Screens Install 15 15 16-Mar-26 03-Apr-26
2350
2830 MIRON CONC 2840 1990, Prep/Pour/Strip Slab on Grade - Brown 3 3 16-Mar-26 18-Mar-26
2410
1520 PEARSON 1430, 1530 1st Floor Interior Steel Stud Framing 10 10 18-Mar-26 31-Mar-26
1360,
1540 ILTENS 2980
1300, 2010, 1st Floor Overhead Rough In - Mechanical 15 15 18-Mar-26 07-Apr-26
1360 1530
1660 PEARSON 1560 1670 2nd Floor Drywall - Hang 3 3 18-Mar-26 20-Mar-26
1990 MERIT 2830, 2890 PEMB - Interior Liner Panels 15 15 19-Mar-26 08-Apr-26
2110
2410 TSF 2330, 2420 Steel - Sequence 7 Running Track Stair Intall/Detail 5 5 19-Mar-26 25-Mar-26
2400,
2940 TRI CITY FP 2830
2840 1630 1st Floor Fire Protection 15 15 19-Mar-26 08-Apr-26
1530 AAAMECH 1520, 1600 1st Floor In Wall Rough In - MEP 15 15 23-Mar-26 10-Apr-26
1540
1670 PEARSON 1660 1680 2nd Floor Drywall - Tape and Sand 5 5 23-Mar-26 27-Mar-26
1680 YOUNGS 1580, 1700, 2nd Floor Paint 8 8 01-Apr-26 10-Apr-26
1670, 2080,
3010 APPLEBY 2420,
1680 2900,
1700 2nd Floor Wall Tile 8 8 03-Apr-26 14-Apr-26
2010 PRICEELEC 1540, 1830 Permenant Power 1 1 08-Apr-26 08-Apr-26
1650
1830 OTIS 1270, 1740, Elevator Installation 15 15 09-Apr-26 29-Apr-26
2010 2120
Actual Work
Remaining Work Please review the activities for which you are responsible and the relationships to the activities of other
Critical Remaining Work trades. If you have questions or comments, please contact Patrick Myers & Corey Boyles immediately. If
Milestone we receive no comments from you by 5 workings days, we will assume a lack of response to be your
agreement and commitment to the durations, relationships, and sequencing of this plan. As always, we will
attempt to improve upon the dates shown. Periodic updates will be distributed as the project progresses.
Sources
- revize: Attachment (GUStiweSiMHBuDC7PDhsDsVSgrKkbF.pdf) — where it was found ↗ first seen Oct 12, 2026
- sharepoint (L-3 - Tiffin Recreation Center Monthly Report - October 2025.pdf) — where it was found ↗ first seen Oct 12, 2026
Attached to agenda item: L-3 Tiffin Recreation Center Monthly Report