Inspections
• See attached “Daily Log Inspections”
Test Results
• Can be found in Procore. See below for accessibility.
• Log into your Procore account and select 250120 – City of Tiffin Community Recreation Center
• Under Project Tools click “Documents” under Core Tools
• In the file tree select the Testing Reports Folder
Quality Issues & Resolution
• N/A
Upcoming Preinstallation Meetings
• Interior steel erection
• Continuing Building Information Modeling with contractors
Bring the passion, keep
moving forward, and stay
focused on the results.
Champion the competitive
spirit, make the most of every
opportunity, and stay hungry.
Owner Progress Report | 250120 November 2025 Miron Construction Co., Inc. | 7
Sheets in this document
- p. 17 Concept Design · Streamline Architects · Tiffin Events Center
- p. 18 Concept Design · Streamline Architects · Tiffin Events Center
- p. 19 Concept Design · Streamline Architects · Tiffin Events Center
- p. 20 Concept Design · Streamline Architects · Tiffin Events Center
- p. 21 Concept Design · Streamline Architects · Tiffin Events Center
- p. 22 Concept Design · Streamline Architects · Tiffin Events Center
- p. 23 Concept Design · Streamline Architects · Tiffin Events Center
- p. 24 Concept Design · Hume Architects · Tiffin Events Center
- p. 25 Concept Design · Streamline Architects · Tiffin Events Center
- p. 26 Concept Design · Streamline Architects · Tiffin Events Center
- p. 27 Concept Design · Streamline Architects · Tiffin Events Center
- p. 28 Concept Design · Hume Architects · Tiffin Events Center
- p. 30 Floor Plan
- p. 31 C120 · Final OPD Site Plan · MMS Consultants · Park Place City Center - Part One, Phase Four
- p. 38 A.200 · West Elevation
- p. 39 A.100 · Floor Plan · Level 2
- p. 40 Floor Plan · Basement
- p. 41 A.200 · Building Elevations
- p. 42 A.201 · East Elevation
- p. 43 Floor Plan · Level 2
- p. 44 A.200 · Building Elevations
- p. 45 Floor Plan · Level 2
- p. 46 C200 · Site Layout Plan · Iowa DOT · Constructed as Part of Phase I Improvements
- p. 47 C300 · Site Utilities Plan North · Grove Park Rowhomes
- p. 48 C301 · Site Utilities Plan South · Grove Park Rowhomes
- p. 49 Landscape Plan
- p. 50 Preliminary Plat · Project Total
- p. 51 2 · Preliminary Plat · Grove Park Rowhomes
- p. 52 3 · Preliminary Plat
- p. 91 map
- p. 98 City of Tiffin FY 25-26 Town Hours by Month (chart; data on p. 97)
- p. 134 Site Concrete
- p. 135 Gym Floor and Slab on Grade · MEP