staff report memo · L-3

Tiffin Recreation Center – Project Update

Dated February 17, 2026City Council — regular meeting, February 17, 2026 18 pages

Open the PDF

Page 8 of 18

Text from the PDF text layer; check the PDF for anything that matters.
Construction Summary Schedule Update Scheduled January Activities: Scheduled February Activities: • Foundation backfill (95%) • 2nd floor interior steel • Erection of pre-engineered metal building (100%) • PEMB roofing • PEMB Roofing (35%) • PEMB exterior metal panels • PEMB exterior metal panels (20%) • Locker Room CMU (95%) Manpower Report List of major subcontractors & number of employees onsite: Total number of employees: 25 • AAA Mechanical – 1 • Price Electric – 2 • Cedar Valley Steel – 3 • Seehase Masonry - 6 • Merit Construction – 1 • SG Construction – 8 • Miron Concrete - 2 • Miron Construction Manager - 2 Delays • Weather – See Daily Log Weather Report ‒ 3 days in January • 1/19/2026 – Dangerous cold temperatures -20F below wind chill • 1/22/2026 – High winds picked up during the morning • 1/23/2026 – Dangerous cold temperatures, -20F below wind chill • 1/26/2026 – Dangerous cold temperatures, -20F below wind chill (Day made up on 2/1) Weather Delays (Construction) Scheduled Occurred Left 12 8 4 • Materials & Labor ‒ N/A Deliver unmatched quality, create meaningful Key Issues / Concerns & Recommended Action Steps connections, and craft • Installation progress of exterior metal panels and roof unforgettable experiences in everything we do. Capture what truly matters and find ways to inspire. Owner Progress Report | 250120 January 2026 Miron Construction Co., Inc. | 8

Sources

Attached to agenda item: L-3 Tiffin Recreation Center – Project Update

This document's details as JSON

Data last updated October 15, 2026. Built from the archive's documents; see how the data is built.