Packet: Tiffin City Council Regular Meeting (03/03/2026)
Dated March 3, 2026City Council — regular meeting, March 3, 2026 133 pages
Ord. 2026-524, Ord. 2026-523, Ord. 2025-520, Res. 2026-014, Res. 2026-015, Res. 2026-016, Res. 2026-010, Res. 2026-011, Res. 2026-008, Res. 2026-009, Res. 2026-012, Res. 2026-013
Page 85 of 133
Text read by OCR; check the PDF for anything that matters.Contractor's Application for Payment
Owner: City of Tiffin Owner's Project No.:
Engineer: MSA Professional Services Engineer's Project No.: 13603016
Contractor: Tricon Construction Group Contractor's Project No.:
Project: Water Treatment Plant Upgrades - City of Tiffin
Contract: Water Treatment Plant Upgrades
Application No.: 6R Application Date: 2/20/2026
Application Period: From 1/24/2026 to 2/20/2026
1. Original Contract Price $ 12,182,553.00
2. Net change by Change Orders $ 12,420.34
3. Current Contract Price (Line 1 + Line 2) $ 12,194,973.34
4. Total Work completed and materials stored to date iS 2,506,154.41
(Sum of Column G Lump Sum Total and Column G Unit Price Total) $ 2,506, 154.41
5. Retainage
a 5% X $ 2,333,704.91 Work Completed $ 116,685.25
b. 5% X $ 172,449.50 Stored Materials $ 8,622.48
c. Total Retainage (Line 5.a + Line 5.b) $ 125,307.73
6. Amount eligible to date (Line 4 - Line 5.c) $ 2,380,846.68
7. Less previous payments (Line 6 from prior application) $ 1 823,406.04
8. Amount due this application $ 557,440.64
9. Balance to finish, including retainage (Line 3 - Line 4, plus 5c) $ 9,814,126.66
Contractor's Certification
The undersigned Contractor certifies, to the best of its knowledge, the following:
Contractor: “[ri con Construction Grovp
Signature: arr Y . CTO Date: 2/25 o0se
PAYMENT OF: S 557,440.64
(line 8 or other - attach explanation of the other amount)
Recommended by Engineer Approved by Owner
By: ene— By:
Title: | Senior Project Engineer Title:
Date: = 2/25/2026 Date:
Approved by Funding Agency
By: By:
Title: Title:
Date: Date:
EJCDC® C-620 Contractor's Application for Payment
© National Society of Professional Engineers for EJCDC. All rights reserved.
00 62 \ABesehvOk\dhares\Projects\active\Tiffin WTP (25-012-IA)\3-Tricon\PaymentApplications\Pay Application