Text from the PDF text layer; check the PDF for anything that matters.Change Authorization Request
Dennis Spencer Construction, Inc.
Project: Tiffin Water Treatment Plant
Submitted To: Contractor
Tricon Construction Dennis Spencer Construction
746 58th Ave. CT. SW Attn: Alex Spencer
Cedar Rapids, IA 52404 319-631-2376
[email protected]
Date Description Quantity Unit Rate Extended Rate
2" Water Service COR
Excavator 6 HRS $375.00 $2,250.00
Labor 12 HRS $115.00 $1,380.00
2" Tap 1 EA $550.00 $550.00
12"x2" Saddle 1 EA $159.50 $159.50
2" Corp 1 EA $412.50 $412.50
2" Curb Stop 1 EA $605.00 $605.00
2" CTS HDPE 100 FT $3.03 $303.00
2" SS Insert 1 EA $3.50 $3.50
Tracer Wire 40 FT $0.28 $11.20
Curb Box 1 EA $93.50 $93.50
SS Rod 1 EA $60.50 $60.50
12" Holding Spool 1 EA $450.00 -$450.00
4" MJ Tee 1 EA $210.00 -$210.00
4" MJ Sleeve 1 EA $145.00 -$145.00
4"x6" MJ Reducer 1 EA $160.00 -$160.00
6" Gate Valve 1 EA $1,025.00 -$1,025.00
Valve Box 1 EA $400.00 -$400.00
Install Hydrant 1 LS $900.00 -$900.00
4" Special Radius Bend 1 EA $205.00 $205.00
Sub Total $2,743.70
10% OHP $274.37
Total $3,018.07
Submitted By: Alex Spencer Date: 3/24/26
Sources
- revize: K.4 (ilsOpCSGLeJgWrIuB4PqcWDz92CA6Y.pdf) — where it was found ↗ first seen Oct 12, 2026
Attached to agenda item: K-4 Discussion and Consideration of Change Order #2 – Tricon Construction – Tiffin Water...
Data last updated October 15, 2026. Built from the archive's documents; see how the data is built.