contract agreement · K-4
Discussion and Consideration of Change Order #2 – Tricon Construction – Tiffin Water Treatment Facility Upgrade Project – Motion to Approve — K.4
Page 48 of 63
Text from the PDF text layer; check the PDF for anything that matters. CONTRACTOR CHANGE ORDER REQUEST
SUMMARY
Project Name: TIFFIN WWT Date: 11/20/2025
Project Number:
Prime Contractor Direct Costs TRICON
Description of Change:
DUCT ADD IN MMC ROOM
Prime Contractor Direct Costs
Additive Costs
HVAC Materials $ 220.00
Plumbing Materials $ -
HVAC Labor 16.00 Hours @ Rate $ 120.00 $ 1,920.00
Plumbing Labor 0.00 Hours @ Rate $ 120.00 $ -
Hydronic $ -
Insulation $ 248.72
Core-Drilling $ -
Test & Balance $ 500.00
Permits $ -
Equipment Rental $ -
Travel/Per Diems $ -
Subtotal of Additive $ 2,888.72
Deductive Costs
HVAC Materials $ -
Plumbing Materials $ -
HVAC Labor 0.00 Hours @ Rate $ 120.00 $ -
Plumbing Labor 0.00 Hours @ Rate $ 120.00 $ -
Hydronic $ -
Insulation $ -
Core-Drilling $ -
Controls Contractor $ -
Permits $ -
Equipment Rental $ -
Travel/Per Diems $ -
Subtotal of Deductive Costs $ -
Subtotal $ 2,888.72
Total OH&P Rate 10% $ 288.87
$ 288.87
Total Change Order Request $ 3,177.59
Approvals
Brian Kraus, Vice President Date
Fosters Kraus Plumbing, Heating, & Air
Name: Date:
General Contractor:
Sources
- revize: K.4 (ilsOpCSGLeJgWrIuB4PqcWDz92CA6Y.pdf) — where it was found ↗ first seen Oct 12, 2026
Attached to agenda item: K-4 Discussion and Consideration of Change Order #2 – Tricon Construction – Tiffin Water...
Data last updated October 17, 2026. Built from the archive's documents; see how the data is built.