Discussion and Consideration of Change Order #2 – Tricon Construction – Tiffin Water Treatment Facility Upgrade Project – Motion to Approve — K.4

Open the PDF Searchable (OCR) PDF

Page 12 of 63

Text from the PDF text layer; check the PDF for anything that matters.
Tiffin WTPU: Transformer Pad Relocation COR Refer to RFI #4 Tricon: Labor: Hours Rate Total Laborer 3 $ 69.50 $ 208.50 Tricon: Material: Product Cost Total Bollards $ - $ - Bollards Covers + Shipping (U-Line) $ 45.00 $ 210.86 316 SS Anchors $ 35.00 $ 70.00 316 SS Anchor Nuts $ 0.61 $ 9.76 316 SS Anchor Washers $ 0.43 $ 6.88 Anchor Epoxy $ 60.00 $ 60.00 Rubber Pads under Bollards $ 13.78 $ 55.12 Misc drill bits for anchors $ 50.00 $ 50.00 $ 462.62 TOTAL $ 671.12