contract agreement · K-2
Discussion and Consideration of Change Order #14 – Boomerang Corporation – North Park Road Improvements Project – Motion to Approve — K.2
Page 6 of 18
Text from the PDF text layer; check the PDF for anything that matters. 0830: Contract unit bid price.
0900: Contract unit bid price.
0920: Contract unit bid price.
1000: Contract unit bid price.
0340: Contract unit bid price.
0480: Contract unit bid price.
0950: Contract unit bid price.
8170: Agreed unit price.
8180: Agreed unit price.
8190: Agreed unit price.
8200: Agreed unit price.
8210: Agreed unit price.
D-Justification for cost(s)
8170: Agreed unit price. Boomerang has provided invoices for the new structure being cast-in-place. This includes the price from J&L Construction for the construction of the
structure and a breakdown of labor cost from Boomerang for the excavation and backfill of the structure. Boomerang has also provided a breakdown of the labor costs for the
excavation and backfill of the original, as-bid structure. When compared with the original cost for the excavation and backfill, the proposed cost is considered reasonable. Unit
price includes Prime Contractor markup of 10% per 1109.03,3.
8180: Agreed unit price. Unit Price ($65.00/LF) is significantly below the average unit bid price of the same item ($168.32/LF) when compared with the Summary of Awarded
Contract Unit Prices for the item from February 2025 to January 2026. It is acknowledged that the price in the Summary may reflect low quantities, and so we could consider the
bid prices of 8 IN. and 12 IN. in the Summary and as part of the original bid package for this specific project. The Agreed unit price ($65.00/LF) falls in between the 8 IN. and the
12 IN. in both cases. Unit price includes Prime Contractor markup of 10% per 1109.03,3.
Change Order Details: 03/30/2026
52-7662-615 Page 5 of 16
Sources
- revize: K.2 (1DT6DpboChvbTnoksN38QC8QMLUNll.pdf) — where it was found ↗ first seen Oct 12, 2026
Attached to agenda item: K-2 Discussion and Consideration of Change Order #14 – Boomerang Corporation – North Park...
Data last updated October 15, 2026. Built from the archive's documents; see how the data is built.