contract agreement · K-2

Discussion and Consideration of Change Order #14 – Boomerang Corporation – North Park Road Improvements Project – Motion to Approve — K.2

Open the PDF

Page 5 of 18

Text from the PDF text layer; check the PDF for anything that matters.
0480: Remove Class III 21in RCP storm sewer from project, pipe section P-24 will be upsized to 24in RCP to accommodate storm flows from Homemaker's 0950: Remove 8in DIP gate valve, Homemaker's water service(s) upsized to 10in, so 8in gate valve is no longer needed. 8170: Add SW-403 MODIFIED cast-in-place for storm structure S-06. SW-403 MODIFIED previously designed for S-06 is removed from the project. Upsize of this structure was necessary to accommodate tie in of 66in RCP to be installed by Homemaker's. See sheet M.11 and M.12 for revisions. 8180: Add 10" PVC to accommodate upsizing of Homemaker's water services from 8in to 10in. 8190: Add 10" gate valves to accommodate upsizing of Homemaker's water services from 8in to 10in. 8200: Add new well for structure I-22. New well furnish only, to accommodate 8in HDPE tie in from Homemaker's. See sheet M.09 for revisions. 8210: Add new well for structure S-05. New well furnish only to accommodate 30in RCP tie in from Homemaker's. See sheet M.10 for revisions. C-Settlement for cost(s) of change 0110: Contract unit bid price. 0130: Contract unit bid price. 0420: Contract unit bid price. 0490: Contract unit bid price. 0530: Contract unit bid price. 0640: Contract unit bid price. 0670: Contract unit bid price. 0760: Contract unit bid price. 0770: Contract unit bid price. 0800: Contract unit bid price. Change Order Details: 03/30/2026 52-7662-615 Page 4 of 16

Sources

Attached to agenda item: K-2 Discussion and Consideration of Change Order #14 – Boomerang Corporation – North Park...

This document's details as JSON

Data last updated October 15, 2026. Built from the archive's documents; see how the data is built.