Discussion and Consideration of Change Order #14 – Boomerang Corporation – North Park Road Improvements Project – Motion to Approve — K.2
Page 16 of 18
Text from the PDF text layer; check the PDF for anything that matters. Line Number Item ID Unit Quantity Unit Price Extension
INTAKE, SW-509, WELL ONLY
Reason: Add new well for structure I-22. New well furnish only, to accommodate 8in HDPE tie in from Homemaker's. See sheet M.09 for revisions.
Funding Details
52-7662-615-CAT-2 ROADWAY ITEMS - DIVISION 2 1.000 $1,796.850 $1,796.85
8210 2599-9999005 EACH 1.000 $2,117.500 $2,117.50
('EACH' ITEM): MANHOLE, STORM SEWER, SW-401, 60 IN., WELL ONLY
Reason: Add new well for structure S-05. New well furnish only to accommodate 30in RCP tie in from Homemaker's. See sheet M.10 for revisions.
Funding Details
52-7662-615-CAT-2 ROADWAY ITEMS - DIVISION 2 1.000 $2,117.500 $2,117.50
5 items Total: $78,059.35
Funding Summary
Fund Package Original Amount Authorized Amount Pending Change Revised Amount
52-7662-615-CAT-1 ROADWAY ITEMS $4,872,701.91 $4,897,063.66 -$30,295.40 $4,866,768.26
52-7662-615-CAT-2 ROADWAY ITEMS - DIVISION 2 $586,190.00 $603,930.80 $83,750.35 $687,681.15
52-7662-615-CAT-3 NON-PARTICIPATING $0.00 $0.00 $0.00 $0.00
3 fund packages $5,458,891.91 $5,500,994.46 $53,454.95 $5,554,449.41
Change Order Details: 03/30/2026
52-7662-615 Page 15 of 16
Sources
- revize: K.2 (1DT6DpboChvbTnoksN38QC8QMLUNll.pdf) — where it was found ↗ first seen Oct 12, 2026
Attached to agenda item: K-2 Discussion and Consideration of Change Order #14 – Boomerang Corporation – North Park...