Line Number Item ID Unit Quantity Unit Price Extension
Section: 0001 - STP-U-7662(615)--70-52, ROADWAY ITEMS
8170 2435-0140310 EACH 1.000 $46,500.000 $46,500.00
MANHOLE, STORM SEWER, SW-403 MODIFIED
Reason: Add SW-403 MODIFIED cast-in-place for storm structure S-06. SW-403 MODIFIED previously designed for S-06 is removed from the project. Upsize of this structure
was necessary to accommodate tie in of 66in RCP to be installed by Homemaker's. See sheet M.11 and M.12 for revisions. This item to be constructed according to the Contractor's
approved design submittal.
Funding Details
52-7662-615-CAT-2 ROADWAY ITEMS - DIVISION 2 1.000 $46,500.000 $46,500.00
8180 2554-0114010 LF 233.000 $65.000 $15,145.00
WATER MAIN, TRENCHED, POLYVINYL CHLORIDE PIPE (PVC), 10 IN.
Reason: Add 10" PVC to accommodate upsizing of Homemaker's water services from 8in to 10in.
Funding Details
52-7662-615-CAT-2 ROADWAY ITEMS - DIVISION 2 233.000 $65.000 $15,145.00
8190 2554-0207010 EACH 2.000 $6,250.000 $12,500.00
VALVE, GATE, DIP, 10 IN.
Reason: Add 10" gate valves to accommodate upsizing of Homemaker's water services from 8in to 10in.
Funding Details
52-7662-615-CAT-2 ROADWAY ITEMS - DIVISION 2 2.000 $6,250.000 $12,500.00
8200 2435-0250902 EACH 1.000 $1,796.850 $1,796.85
Change Order Details: 03/30/2026
52-7662-615 Page 14 of 16
Sources
- revize: K.2 (1DT6DpboChvbTnoksN38QC8QMLUNll.pdf) — where it was found ↗ first seen Oct 12, 2026
Attached to agenda item: K-2 Discussion and Consideration of Change Order #14 – Boomerang Corporation – North Park...
Data last updated October 16, 2026. Built from the archive's documents; see how the data is built.