Discussion and Consideration of Change Order #14 – Boomerang Corporation – North Park Road Improvements Project – Motion to Approve — K.2
Page 14 of 18
Text from the PDF text layer; check the PDF for anything that matters. Line Number Item ID Unit Unit Price Current Change Revised
Quantity Amount Quantity Amount Quantity Amount
0920 2554-0203000 LB $16.000 3,070.000 $49,120.00 210.000 $3,360.00 3,280.000 $52,480.00
FITTINGS BY WEIGHT, DUCTILE IRON
Reason: Add quantity to account for an additional 10" service lines to the Homemakers site at Mopar Drive and on the north side of the project. See sheets C.24, MWM.05, and
MWM.07 for revisions.
Funding Details
52-7662-615-CAT-1 ROADWAY ITEMS 0.000 $0.00 0.000 $0.00 0.000 $0.00
52-7662-615-CAT-2 ROADWAY ITEMS - DIVISION 2 3,070.000 $49,120.00 210.000 $3,360.00 3,280.000 $52,480.00
52-7662-615-CAT-3 NON-PARTICIPATING 0.000 $0.00 0.000 $0.00 0.000 $0.00
1000 2554-0211002 EACH $2,200.000 2.000 $4,400.00 2.000 $4,400.00 4.000 $8,800.00
FLUSHING DEVICE (BLOWOFF), 2 IN.
Reason: Add quantity to account for an additional 10" service lines to the Homemakers site at Mopar Drive and on the north side of the project. See sheets C.24, MWM.05, and
MWM.07 for revisions.
Funding Details
52-7662-615-CAT-1 ROADWAY ITEMS 0.000 $0.00 0.000 $0.00 0.000 $0.00
52-7662-615-CAT-2 ROADWAY ITEMS - DIVISION 2 2.000 $4,400.00 2.000 $4,400.00 4.000 $8,800.00
52-7662-615-CAT-3 NON-PARTICIPATING 0.000 $0.00 0.000 $0.00 0.000 $0.00
16 items Totals $1,775,651.15 -$24,604.40 $1,751,046.75
Change Order Details: 03/30/2026
52-7662-615 Page 13 of 16
Sources
- revize: K.2 (1DT6DpboChvbTnoksN38QC8QMLUNll.pdf) — where it was found ↗ first seen Oct 12, 2026
Attached to agenda item: K-2 Discussion and Consideration of Change Order #14 – Boomerang Corporation – North Park...
Data last updated October 16, 2026. Built from the archive's documents; see how the data is built.