Discussion and Consideration of Change Order #14 – Boomerang Corporation – North Park Road Improvements Project – Motion to Approve — K.2
Page 17 of 18
Text from the PDF text layer; check the PDF for anything that matters.Time Limit Changes
Type Original Deadline Current Deadline Pending Extension Pending Deadline
Working Days 200.0 Days 202.0 Days 6.0 Days 208.0 Days
Working Days, Late Start Date - 04/07/2025, Liquidated Damage Rate - 2,000
Reason: Add 6 working days to accommodate additional labor and time needed to complete new items and quantity changes for Change Order #14.
1 time limit
Attachments
Document Name Description Submission Date
S-06, SW-403 MODIFIED, Contractor designed stru 03/30/2026 07:50 AM
13603023_SDR_3__S-06__MOD-403_.pdf 13603023 SDR#3_ S-06 (MOD-403).pdf
cture. EDT
24060_-_RFC__013_-_CO__13_-_Homemaker 24060 - RFC #013 - CO #13 - Homemaker 03/02/2026 09:30 AM
s.pdf s.pdf EST
03/05/2026 11:01 AM
Change_Order__14_time_breakdown.pdf Change Order #14 time breakdown.pdf
EST
3 attachments
Change Order Details: 03/30/2026
52-7662-615 Page 16 of 16
Sources
- revize: K.2 (1DT6DpboChvbTnoksN38QC8QMLUNll.pdf) — where it was found ↗ first seen Oct 12, 2026
Attached to agenda item: K-2 Discussion and Consideration of Change Order #14 – Boomerang Corporation – North Park...
Data last updated October 16, 2026. Built from the archive's documents; see how the data is built.