Discussion and Consideration of Change Order #14 – Boomerang Corporation – North Park Road Improvements Project – Motion to Approve — K.2

Open the PDF

Page 17 of 18

Text from the PDF text layer; check the PDF for anything that matters.
Time Limit Changes Type Original Deadline Current Deadline Pending Extension Pending Deadline Working Days 200.0 Days 202.0 Days 6.0 Days 208.0 Days Working Days, Late Start Date - 04/07/2025, Liquidated Damage Rate - 2,000 Reason: Add 6 working days to accommodate additional labor and time needed to complete new items and quantity changes for Change Order #14. 1 time limit Attachments Document Name Description Submission Date S-06, SW-403 MODIFIED, Contractor designed stru 03/30/2026 07:50 AM 13603023_SDR_3__S-06__MOD-403_.pdf 13603023 SDR#3_ S-06 (MOD-403).pdf cture. EDT 24060_-_RFC__013_-_CO__13_-_Homemaker 24060 - RFC #013 - CO #13 - Homemaker 03/02/2026 09:30 AM s.pdf s.pdf EST 03/05/2026 11:01 AM Change_Order__14_time_breakdown.pdf Change Order #14 time breakdown.pdf EST 3 attachments Change Order Details: 03/30/2026 52-7662-615 Page 16 of 16

Sources

Attached to agenda item: K-2 Discussion and Consideration of Change Order #14 – Boomerang Corporation – North Park...

This document's details as JSON

Data last updated October 16, 2026. Built from the archive's documents; see how the data is built.