contract agreement · K-2
Discussion and Consideration of Pay Application #8 – Tricon Construction – Tiffin Water Treatment Facility Upgrade Project – Motion to Approve — K.2
Page 3 of 12
Text read by the vision model; check the PDF for anything that matters.Progress Estimate - Lump Sum Work
Owner: City of Tiffin
Engineer: MSA Professional Services
Contractor: Tricon Construction Group
Project: Water Treatment Plant Upgrades - City of Tiffin
Contract:
Contractor's Application for Payment
Owner's Project No.:
Engineer's Project No.: 13603016
Contractor's Project No.:
Application No.: 8
Application Period: From 03/28/26 to 04/23/26
Application Date: 04/24/26
<table>
<tr>
<th>A</th>
<th>B</th>
<th>C</th>
<th>D</th>
<th>E</th>
<th>F</th>
<th>G</th>
<th>H</th>
<th>I</th>
</tr>
<tr>
<th>Item No.</th>
<th>Description</th>
<th>Scheduled Value ($)</th>
<th>(D + E) From Previous Application ($)</th>
<th>This Period ($)</th>
<th>Materials Currently Stored (not in D or E) ($)</th>
<th>Work Completed and Materials Stored to Date (D + E + F) ($)</th>
<th>% of Scheduled Value (G / C) (%)</th>
<th>Balance to Finish (C - G) ($)</th>
</tr>
<tr>
<td colspan="9">Original Contract</td>
</tr>
<tr>
<td>00</td>
<td>General Requirements</td>
<td></td>
<td></td>
<td></td>
<td></td>
<td></td>
<td></td>
<td></td>
</tr>
<tr>
<td>01</td>
<td>General Conditions</td>
<td>$588,953.00</td>
<td>234,461.22</td>
<td>39,076.87</td>
<td></td>
<td>273,538.09</td>
<td>46%</td>
<td>315,414.91</td>
</tr>
<tr>
<td>02</td>
<td>Bond/Buider's Risk Insurance</td>
<td>$199,542.00</td>
<td>199,542.00</td>
<td></td>
<td></td>
<td>199,542.00</td>
<td>100%</td>
<td>-</td>
</tr>
<tr>
<td>03</td>
<td>Allowance EP1 - Generator & ATS</td>
<td>$329,890.00</td>
<td>329,890.00</td>
<td></td>
<td></td>
<td>329,890.00</td>
<td>100%</td>
<td>-</td>
</tr>
<tr>
<td>04</td>
<td>Allowance EP2 Electrical Equipment Line item 167</td>
<td></td>
<td></td>
<td></td>
<td></td>
<td></td>
<td></td>
<td>-</td>
</tr>
<tr>
<td>05</td>
<td>Allowance - Electrical Service</td>
<td>$5,000.00</td>
<td></td>
<td></td>
<td></td>
<td></td>
<td>0%</td>
<td>5,000.00</td>
</tr>
<tr>
<td>06</td>
<td>Mobilization</td>
<td>$350,000.00</td>
<td>240,000.00</td>
<td></td>
<td></td>
<td>240,000.00</td>
<td>69%</td>
<td>110,000.00</td>
</tr>
<tr>
<td>07</td>
<td>Site Testing</td>
<td>$53,736.00</td>
<td>13,383.19</td>
<td>1,354.59</td>
<td></td>
<td>14,737.78</td>
<td>27%</td>
<td>38,998.22</td>
</tr>
<tr>
<td>08</td>
<td>Traffic Control</td>
<td>$10,000.00</td>
<td>1,000.00</td>
<td>1,000.00</td>
<td></td>
<td>2,000.00</td>
<td>20%</td>
<td>8,000.00</td>
</tr>
<tr>
<td>09</td>
<td>Portable Toilets</td>
<td>$5,400.00</td>
<td>1,187.20</td>
<td>148.40</td>
<td></td>
<td>1,335.60</td>
<td>25%</td>
<td>4,064.40</td>
</tr>
<tr>
<td>10</td>
<td>Dumpster</td>
<td>$14,600.00</td>
<td>3,000.00</td>
<td>500.00</td>
<td></td>
<td>3,500.00</td>
<td>24%</td>
<td>11,100.00</td>
</tr>
<tr>
<td>11</td>
<td>Concrete Washout Pit</td>
<td>$2,400.00</td>
<td>240.00</td>
<td>240.00</td>
<td></td>
<td>480.00</td>
<td>20%</td>
<td>1,920.00</td>
</tr>
<tr>
<td>12</td>
<td>Erosion Control</td>
<td>$8,250.00</td>
<td>3,500.00</td>
<td></td>
<td></td>
<td>3,500.00</td>
<td>42%</td>
<td>4,750.00</td>
</tr>
<tr>
<td>13</td>
<td></td>
<td></td>
<td></td>
<td></td>
<td></td>
<td></td>
<td></td>
<td>-</td>
</tr>
<tr>
<td>14</td>
<td>Existing Conditions</td>
<td></td>
<td></td>
<td></td>
<td></td>
<td></td>
<td></td>
<td>-</td>
</tr>
<tr>
<td>15</td>
<td>Structure Demolition</td>
<td>$33,445.00</td>
<td></td>
<td></td>
<td></td>
<td></td>
<td>0%</td>
<td>33,445.00</td>
</tr>
<tr>
<td>16</td>
<td></td>
<td></td>
<td></td>
<td></td>
<td></td>
<td></td>
<td></td>
<td>-</td>
</tr>
<tr>
<td>17</td>
<td>Concrete</td>
<td></td>
<td></td>
<td></td>
<td></td>
<td></td>
<td></td>
<td>-</td>
</tr>
<tr>
<td>18</td>
<td>Structure 10 - Existing Building</td>
<td></td>
<td></td>
<td></td>
<td></td>
<td></td>
<td></td>
<td>-</td>
</tr>
<tr>
<td>19</td>
<td>Rebar - Materials</td>
<td>$54,588.00</td>
<td></td>
<td></td>
<td></td>
<td></td>
<td>0%</td>
<td>54,588.00</td>
</tr>
<tr>
<td>20</td>
<td>Rebar - Labor</td>
<td>$46,399.80</td>
<td></td>
<td></td>
<td></td>
<td></td>
<td>0%</td>
<td>46,399.80</td>
</tr>
<tr>
<td>21</td>
<td>Concrete - Materials</td>
<td>$165,884.00</td>
<td></td>
<td></td>
<td></td>
<td></td>
<td>0%</td>
<td>165,884.00</td>
</tr>
<tr>
<td>22</td>
<td>Concrete - Labor</td>
<td>$91,308.20</td>
<td></td>
<td></td>
<td></td>
<td></td>
<td>0%</td>
<td>91,308.20</td>
</tr>
<tr>
<td>23</td>
<td>Structure 20 - RO Building</td>
<td></td>
<td></td>
<td></td>
<td></td>
<td></td>
<td></td>
<td>-</td>
</tr>
<tr>
<td>24</td>
<td>Rebar - Materials</td>
<td>$84,556.00</td>
<td>76,100.40</td>
<td></td>
<td></td>
<td>76,100.40</td>
<td>90%</td>
<td>8,455.60</td>
</tr>
</table>
Sources
- revize: K.2 (UewULoFEgkp9XcjJXN7T0N0S8Nwqrw.pdf) — where it was found ↗ first seen Oct 12, 2026
Attached to agenda item: K-2 Discussion and Consideration of Pay Application #8 – Tricon Construction – Tiffin...
Data last updated October 15, 2026. Built from the archive's documents; see how the data is built.