contract agreement · K-2

Discussion and Consideration of Pay Application #8 – Tricon Construction – Tiffin Water Treatment Facility Upgrade Project – Motion to Approve — K.2

Open the PDF Searchable (OCR) PDF

Page 2 of 12

Text read by the vision model; check the PDF for anything that matters.
Contractor's Application for Payment Owner: City of Tiffin Engineer: MSA Professional Services Contractor: Tricon Construction Group Project: Water Treatment Plant Upgrades - City of Tiffin Contract: Water Treatment Plant Upgrades Owner's Project No.: 13603016 Engineer's Project No.: 13603016 Contractor's Project No.: Application No.: 8 Application Date: 4/24/2026 Application Period: From 3/28/2026 to 4/23/2026 <table> <tr> <th> </th> <th> </th> <th> </th> </tr> <tr> <td>1. Original Contract Price</td> <td>$</td> <td>12,182,553.00</td> </tr> <tr> <td>2. Net change by Change Orders</td> <td>$</td> <td>12,420.34</td> </tr> <tr> <td>3. Current Contract Price (Line 1 + Line 2)</td> <td>$</td> <td>12,194,973.34</td> </tr> <tr> <td>4. Total Work completed and materials stored to date<br>(Sum of Column G Lump Sum Total and Column G Unit Price Total)</td> <td>$</td> <td>4,101,519.57</td> </tr> <tr> <td>5. Retainage<br>a. 5% X $ 3,808,393.49 Work Completed<br>b. 5% X $ 293,126.08 Stored Materials<br>c. Total Retainage (Line 5.a + Line 5.b)</td> <td>$</td> <td>190,419.67<br>14,656.30<br>205,075.97</td> </tr> <tr> <td>6. Amount eligible to date (Line 4 - Line 5.c)</td> <td>$</td> <td>3,896,443.60</td> </tr> <tr> <td>7. Less previous payments (Line 6 from prior application)</td> <td>$</td> <td>2,718,030.93</td> </tr> <tr> <td>8. <b>Amount due this application</b></td> <td>$</td> <td>1,178,412.67</td> </tr> <tr> <td>9. Balance to finish, including retainage (Line 3 - Line 4, plus 5c)</td> <td>$</td> <td>8,298,529.74</td> </tr> </table> Contractor's Certification The undersigned Contractor certifies, to the best of its knowledge, the following: Contractor: Tricon Construction Group Signature: Mary K. Stone Date: 4/29/2026 PAYMENT OF: $1,178,412.67 (line 8 or other - attach explanation of the other amount) Recommended by Engineer By: [signature] Title: Senior Project Engineer Date: April 29, 2026 Approved by Funding Agency By: [signature] Title: [title] Approved by Owner By: [signature] Title: [title] Date: ____________________________ Date: ____________________________

Sources

Attached to agenda item: K-2 Discussion and Consideration of Pay Application #8 – Tricon Construction – Tiffin...

This document's details as JSON

Data last updated October 15, 2026. Built from the archive's documents; see how the data is built.