Text read by the vision model; check the PDF for anything that matters.Morgan stated that everyone is unhappy with the situation, but this is a way to get something done.
Potter stated that at most, the City would lose $300.00 if the outside is done first.
Baker reported that Gish will send in another crew as soon as this is approved.
Cox asked about the guarantee on epoxy.
Baker stated that the tower is guaranteed for one year, which is standard on this type of construction.
Motion Kobold second Morgan to approve change order no. 2 which reads:
"Change is contract completion date to August 27, 1984. Contract liquidated damages of $100.00 per day shall accrue for each day after August 27, 1984 until the pit repair and painting is completed. Contract liquidated damages shall not accrue after the painting is completed while the paint is curing or the tank is being disinfected. The contractor shall repair interior pitting in the riser pipe and lower part of the bowl with Tenemed 61-1400 Seam Sealer Solventless Epoxy-Polyamide Sealer at no additional cost to the Owner. Roll call vote: Kobold, aye; Morgan, aye; Spivey, nay; Cox, aye. Carried.
Motion Cox second Morgan to adjourn at 6:30 p.m. Carried unanimously.
[Signature]
Glenn R. Potter, Mayor
[Signature]
Adelia S. Kern, Clerk-Treasurer
Sent to "The Leader" on Sept. 4, 1984 for publication.