Text read by the vision model; check the PDF for anything that matters.Date: July 6, 2021
To: Mr. Ben Carhoff
Project: Original Town Urbanization - Phase 2
Re: COR 4 - Flowable Mortar
Rathje #: 7187
I am hereby submitting the following change order request for 6 CY of flowable mortar required to abandon 100 LF of 15" RCP Storm Sewer. If additional flowable mortar is needed, we will use the unit price of $152.25 which includes the bond.
<table>
<tr>
<th>Description</th>
<th>Qty.</th>
<th>Unit</th>
<th>Unit Price</th>
<th>Mark Up</th>
<th>Extended Price</th>
</tr>
<tr>
<td>Flowable Mortar</td>
<td>6.00</td>
<td>CY</td>
<td>$ 150.00</td>
<td>-</td>
<td>$ 900.00</td>
</tr>
<tr>
<td></td>
<td></td>
<td></td>
<td></td>
<td>Subtotal</td>
<td>$ 900.00</td>
</tr>
<tr>
<td></td>
<td></td>
<td></td>
<td></td>
<td>Bond</td>
<td>$ 13.50</td>
</tr>
<tr>
<td></td>
<td></td>
<td></td>
<td></td>
<td>Total</td>
<td>$ 913.50</td>
</tr>
</table>
Please call if you have any questions.
Respectfully,
J. Shawn Lueth, PE
319.325.9719