Text read by the vision model; check the PDF for anything that matters.CHANGE ORDER #3
DATE: 6 July, 2021
Change Order No: 3 (Three)
Agreement Date: 5 May, 2020
PROJECT: Original Town Urbanization Project: Phase Two HFC#12218.13123
OWNER: City of Tiffin, IA
CONTRACTOR: Rathje Construction
DESCRIPTION OF CHANGES TO CONTRACT DOCUMENTS:
Abandonment in place of previously unknown storm sewers by filling pipe with flowable mortar. Establish a cubic yard (CY) price for future use of material; $152.25/CY.
CONTRACT PRICE CHANGES:
<table>
<tr>
<th>Original CONTRACT PRICE:</th>
<td>$ 1,824,618.96</td>
</tr>
<tr>
<th>CONTRACT with LAST CHANGE ORDER:</th>
<td>$1,816,673.96</td>
</tr>
<tr>
<th>THIS CHANGE ORDER AMOUNT:</th>
<td>$ 913.50</td>
</tr>
<tr>
<th>NEW CONTRACT PRICE:</th>
<td>$ 1,817,587.46</td>
</tr>
</table>
CONTRACT TIME CHANGES
CONTRACT TIME (increased)(decreased): N/A
NEW Completion Date: N/A
APPROVALS REQUIRED: To be effective this Order must be approved by the OWNER.
OWNER: ________________________________
CONTRACTOR: See Attached
ENGINEER: ________________________________
Sources
- sharepoint (K-2 - Change Order 3 - Original Town Phase Two - Rathje Construction.pdf) — where it was found ↗ first seen Oct 12, 2026
Data last updated October 15, 2026. Built from the archive's documents; see how the data is built.