staff report memo · E-6
Approval of Changer Order #18 - Boomerang Construction Group - North Park Road Improvements Project — E-6
Page 5 of 6
Text from the PDF text layer; check the PDF for anything that matters. Line Number Item ID Unit Quantity Unit Price Extension
Change Order #17. This quantity was initially included under category 1 federal funding in Change Order #17, then incorrectly approved in Appia. Change Order #17 cannot be
unapproved in Appia, so the modified subbase quantity funding category error will be removed with this change order.
Funding Details
52-7662-615-CAT-2 ROADWAY ITEMS - DIVISION 2 44.445 $86.000 $3,822.27
1 item Total: $3,822.27
Funding Summary
Fund Package Original Amount Authorized Amount Pending Change Revised Amount
52-7662-615-CAT-1 ROADWAY ITEMS $4,872,701.91 $4,878,090.53 -$3,822.27 $4,874,268.26
52-7662-615-CAT-2 ROADWAY ITEMS - DIVISION 2 $586,190.00 $708,886.15 $3,822.27 $712,708.42
New Fund 52-7662-615-CAT-3 NON-PARTICIPATINGackage $0.00 $0.00 $0.00 $0.00
3 fund packages $5,458,891.91 $5,586,976.68 $0.00 $5,586,976.68
Change Order Details: 08/26/2026
52-7662-615 Page 4 of 4
Sources
- revize: E-6 (hOhWEp62VdqTBpONdCx5jblp5RC4GA.pdf) — where it was found ↗ first seen Oct 12, 2026
Attached to agenda item: E-6 Approval of Changer Order #18 - Boomerang Construction Group - North Park Road...
Data last updated October 15, 2026. Built from the archive's documents; see how the data is built.