staff report memo · E-6
Approval of Changer Order #18 - Boomerang Construction Group - North Park Road Improvements Project — E-6
Page 6 of 6
Text from the PDF text layer; check the PDF for anything that matters.Doc Express® Document Signing History
Contract: 52-7662-615 Document: change_order-18-20260825
This document is in the process of being signed by all required signatories using the Doc Express® service.
Following are the signatures that have occurred so far.
Date Signed By
Keegan Parizek
08/26/2026 Boomerang Corp.
Electronic Signature
(Approved by Contractor)
Kelda Hankins
MSA Professional Svs
08/26/2026
Electronic Signature
(Recommended by Engineer / Approved)
(Approved by PIRC (when applicable))
(Approved by Administering Bureau or designee)
(Approved by FHWA (when applicable))
Sources
- revize: E-6 (hOhWEp62VdqTBpONdCx5jblp5RC4GA.pdf) — where it was found ↗ first seen Oct 12, 2026
Attached to agenda item: E-6 Approval of Changer Order #18 - Boomerang Construction Group - North Park Road...
Data last updated October 15, 2026. Built from the archive's documents; see how the data is built.