staff report memo · E-6
Approval of Changer Order #18 - Boomerang Construction Group - North Park Road Improvements Project — E-6
Page 4 of 6
Text from the PDF text layer; check the PDF for anything that matters. Line Number Item ID Unit Unit Price Current Change Revised
Quantity Amount Quantity Amount Quantity Amount
Reason: This change order corrects a modified subbase bid item quantity change from Change Order #17. For this work this needs to be a new non participating item and remove
the increase to 0080 from change order #17. Remove modified subbase overrun quantity from Change Order #17. This quantity was initially included under category 1 federal
funding in Change Order #17, then incorrectly approved in Appia. Change Order #17 cannot be unapproved in Appia, so the modified subbase quantity funding category error will
be removed with this change order.
Funding Details
52-7662-615-CAT-1 ROADWAY ITEMS 4,779.890 $205,535.27 -88.890 -$3,822.27 4,691.000 $201,713.00
52-7662-615-CAT-2 ROADWAY ITEMS - DIVISION 2 0.000 $0.00 0.000 $0.00 0.000 $0.00
New Fund 52-7662-615-CAT-3 NON-PARTICIPATINGackage 0.000 $0.00 0.000 $0.00 0.000 $0.00
1 item Totals $205,535.27 -$3,822.27 $201,713.00
New Items
Line Number Item ID Unit Quantity Unit Price Extension
Section: 0001 - STP-U-7662(615)--70-52, ROADWAY ITEMS
8270 2115-0100200 CY 44.445 $86.000 $3,822.27
MODIFIED SUBBASE, PLACE ONLY
Reason: Because the roadway has already been constructed with Modified Subbase, the placement of the existing modified subbase has been included for the removal and
reinstallation of the roadway section impacted by this work. This work consists of carefully removing and stockpiling as much of the existing Modified Subbase as possible without
contaminating the material during excavation, then reinstalling the salvaged Modified Subbase after the trench has been properly backfilled. Compensation for this item will be
based on the actual field-measured quantity, for both the removal and reinstallation of the Modified Subbase. The estimated quantity of 88.89 CY is provided solely for bidding
purposes and will be adjusted to reflect the actual quantity required to complete the work. This change order corrects a modified subbase bid item quantity change from Change
Order #17. For this work this needs to be a new non participating item and remove the increase to 0080 from change order #17. Remove modified subbase overrun quantity from
Change Order Details: 08/26/2026
52-7662-615 Page 3 of 4
Sources
- revize: E-6 (hOhWEp62VdqTBpONdCx5jblp5RC4GA.pdf) — where it was found ↗ first seen Oct 12, 2026
Attached to agenda item: E-6 Approval of Changer Order #18 - Boomerang Construction Group - North Park Road...