Text from the PDF text layer; check the PDF for anything that matters. AGENDA ITEM # K-2
The proposed agreement with MSA Professional Services, Inc. is a lump-sum agreement in the
amount of $84,000.
The anticipated schedule is:
Approximate Start Date: October 2026
Approximate Completion Date: February 2027
The agreement provides for final plans, specifications, and an opinion of probable construction
cost.
The agreement identifies a number of services that are outside the current scope and would
require a separate agreement or amendment if needed. These include geotechnical services,
additional survey work, bidding services, construction services, funding applications and
administration, and additional meetings beyond those identified in the agreement.
Development of Well #6 is an important component of planning for Tiffin's continued growth
and future water-system capacity. Completing the design work will allow the City to better
understand the total project cost and requirements for bringing the existing test well into
production.
The proposed agreement provides the engineering services necessary to advance the project
through design, permitting, and preparation of construction documents. Construction and bidding
services are not included in the current agreement and would be addressed separately.
Recommendation
Staff recommends approval of the Professional Services Agreement with MSA Professional
Services, Inc. for design services related to bringing Tiffin Well #6 into service.
ATTACHMENTS: Agreement
2
Sources
- revize: K-2 (fppq6CNYks0mOLG5CzwDV1goxVJUXS.pdf) — where it was found ↗ first seen Oct 12, 2026
Attached to agenda item: K-2 Discussion and Consideration of Professional Services Agreement with MSA for the...
Data last updated October 15, 2026. Built from the archive's documents; see how the data is built.