K-2 - Pay Estimate 6 - Carter and Associates - Trail Phase 7
Page 2 of 3
Text read by the vision model; check the PDF for anything that matters.PARTIAL PAYMENT ESTIMATE NUMBER 6
CONTRACTOR: Carter & Associates
ADDRESS: 395 Westcor Dr.
CITY, STATE, ZIP Coralville, IA 52241
OWNER: City of Tiffin
PROJECT: Trail Phase 7 Project
HFC#17218.218
<table>
<tr>
<th>Date of Completion:</th>
<th>Amount of Contract:</th>
<th>Date of Estimate:</th>
</tr>
<tr>
<td>Original: 6/1/2021</td>
<td>Original: $269,835.84</td>
<td>From: 10-Sep-21</td>
</tr>
<tr>
<td>Revised:</td>
<td>Revised:</td>
<td>(C.O. #) To: 28-Nov-21</td>
</tr>
</table>
<table>
<tr>
<th></th>
<th>THIS PERIOD</th>
<th>TOTAL TO DATE</th>
</tr>
<tr>
<td>Amount Earned</td>
<td>$ 3,274.80</td>
<td>$ 286,608.24</td>
</tr>
<tr>
<td>Add Material Stored On-Site</td>
<td>$ -</td>
<td>$ -</td>
</tr>
<tr>
<td>Subtract Materials Installed On-Site</td>
<td>$ -</td>
<td>$ -</td>
</tr>
<tr>
<td>Subtotal</td>
<td>$ 3,274.80</td>
<td>$ 286,608.24</td>
</tr>
<tr>
<td>Retainage (5%)</td>
<td>$ 163.74</td>
<td>$ 14,330.52</td>
</tr>
<tr>
<td>Previous Payments</td>
<td></td>
<td>$ 240,738.80</td>
</tr>
<tr>
<td>Liquidated Damages Settlement</td>
<td></td>
<td></td>
</tr>
<tr>
<td>Amount Due</td>
<td>$ 3,111.06</td>
<td>$ 31,538.92</td>
</tr>
</table>
Estimated % of Job Complete Based on Amount Earned/Contract Amount only 106%
This does not constitute work completed to date
Is Contractor's Construction Progress on Schedule? YES NO N/A X
I hereby certify that I have carefully inspected the work and as a result of my inspection and to the best of my knowledge and belief, the quantities shown in this estimate are correct and have not been shown in previous estimates and the work has been performed in accordance with the contract documents.
HART-FREDERICK CONSULTANTS P.C.
By: [signature]
Title: Project Engineer
Date: August 12, 2022
Approved by Owner's Representative:
By: ____________________________
Title: ____________________________
(Additional signatures -- if required)
By: ____________________________
Title: ____________________________